    Electrical & Control · Chapter 118Applied

    By Kurnia · Published November 15, 2026 · Version 1 · 21 min read

    Total building blackout and recovery

    first response, generator sets and priority loads, people trapped in lifts, pumps and water, staged restoration, and records and review

    During a dinner in a hotel ballroom, the PLN supply fails because of a storm and the generator set picks up the priority loads, but the rooftop tank runs down because the transfer pump is not on the generator circuit, and when PLN power returns the main breaker trips because every panel is switched on at once. This chapter covers a total building blackout from the building technician’s side: telling a utility outage from a trip inside the building, a first response that puts people first, generator sets and priority loads, motor starting current and step loading, people trapped in lifts as a matter for trained persons, pumps, tanks, and water, food and medicines that must stay cold, staged restoration when utility power returns, and incident records and review. It draws on Permenaker 12/2015 for the division of electrical safety authority, HSE guidance on electrical working practices, United States military facility documents on transfer switches and generator sets, and CDC guidance on food and safety during power outages. Medium-voltage switching, operating a transfer switch manually, connecting a portable generator to a panel, and getting people out of a lift are stated as work for authorized and trained persons.

    High-risk material

    This material involves real hazards. A concept explanation doesn’t replace site procedures, competency, energy isolation, the latest SDS, or a work permit.

    Section you’re reading: Chapter opening

    On a Saturday night, 420 guests are having dinner in a hotel ballroom when a storm cuts the PLN network in the area. The emergency lights come on, the generator set picks up the priority loads within a dozen or so seconds, and one guest lift stops between floors 9 and 10 with two guests inside. Forty minutes later the taps on the upper floors start to weaken: the transfer pump to the rooftop tank turns out not to be on the generator circuit. When PLN power returns, a technician switches on every panel breaker at once so that the ballroom cools quickly, and the main breaker trips. The duty technician needs to know what to do in the first minutes, which loads are entitled to the generator set, what may be done for the guests in the lift, how long water and food will last, and how to bring the building back without blacking it out again.

    Scope

    This chapter covers a total building blackout from the building technician’s side: identifying the source of the outage, first response, priority loads and step loading on the generator set, pumps and water, food and medicines that must stay cold, staged restoration, and records and review. Rules and tests for hospital generator sets are in Chapter 31 · Buildings & Facilities on hospital facility and utility management.

    Generator sets, transfer switches, and backfeed are in Chapter 36 on generator sets, transfer switches, and standby supply; generator fuel in Chapter 23 · Fluids & Thermal; the medium-voltage substation in Chapter 110; UPS in Chapter 107; emergency lighting in Chapter 106; lift emergency response in Chapter 25 · Buildings & Facilities; building water pumps in Chapter 9 · Buildings & Facilities; clean water supply in Chapter 5 · Buildings & Facilities; backflow in Chapter 11 · Buildings & Facilities; wastewater pumps in Chapter 39 · Water & Water Treatment; walk-in cold rooms in Chapter 21 · Fluids & Thermal; the fire alarm panel in Chapter 19 · Buildings & Facilities; LOTO in Chapter 76; incident investigation in Chapter 12 · Safety; and portable generator sets in the R22 chapter on temporary power for events and exhibitions (Chapter 117).

    Outside the building technician’s authority: any switching or work on medium-voltage switchgear, reclosing a breaker that tripped on a fault, operating the transfer switch manually or through a bypass, changing its timer settings, opening live panels, connecting a portable generator set to a fixed panel, and getting people out of a lift. That work belongs to PLN staff, an Ahli K3 bidang listrik (certified electrical K3 expert) or authorized electrician, the generator contractor, and the lift contractor or a person trained to rescue passengers. This chapter gives no medium-voltage switching steps, no steps for operating the transfer switch, and no steps for evacuating people from a lift, and the building technician does not do these things.

    Where the outage comes from: the utility network or inside the building

    A total building blackout is the condition in which the entire normal supply is lost, so that only loads fed by the generator set, the UPS, and emergency lighting batteries stay on.

    A utility outage is visible from outside the building: street lights and neighboring buildings also go dark, and the incoming voltage indicator in the customer substation is off even though the hotel’s own breaker is still closed. Nothing needs to be repaired inside the building; the technician makes sure the generator set and transfer switch are working, reports to the PLN complaints center, and records the time.

    A trip inside the building is different. The neighbors stay lit, but the hotel’s main breaker or switchgear breaker is open, sometimes with a relay flag dropped, a burning smell, or water near the panel. That breaker opened because of a fault, and closing it before the cause is found can strike an arc on the same fault (Chapter 110). If in doubt, treat the outage as a trip inside the building and call an authorized person.

    A power outage does not mean the installation is dead. The generator set can start, the transfer switch can move the load, and utility power can return without warning. HSE guidance asks for equipment to be disconnected from every source of electrical energy before work on any part that has been live or is likely to be live, and mentions the risk of re-energization from a generator under someone else’s control. An outage is therefore not an opportunity to work on panels; electrical work still requires isolation, locking off, and proving dead according to Chapter 76.

    First response: people first

    The first minutes follow the building’s emergency response plan: who leads, who checks the lifts, who goes to the generator room, and how the team communicates when the office telephones are also down. Charged handheld radios and a public address system fed by the UPS become the main tools.

    The order of attention follows the places where people can be hurt: lifts, stairs and corridors that depend on emergency lighting, kitchens cooking over open flames, walk-in cold rooms that may have someone inside, pools and spas, and in hospitals, patients who depend on equipment.

    In the generator room, the technician confirms that the generator set is running, voltage and frequency are normal, the transfer switch has moved the load, and there is no alarm, smoke, fuel leak, or unusual noise. Observations are recorded, not changed. The fire alarm panel and the building management system will show supply faults; the technician records them without resetting or isolating zones (Chapter 19 · Buildings & Facilities).

    If the kitchen hood exhaust fan stops while gas burners are still lit, heat and flue gas build up; the head chef shuts down the gas equipment according to the kitchen procedure. A portable generator set is never run inside the building. CDC asks that generators and other gasoline engines not be run inside a home, basement, or garage, or less than 20 feet (about 6.1 m) from any window, door, or vent, because carbon monoxide can build up and kill; CDC also recommends battery flashlights rather than candles.

    Generator sets, priority loads, and step loading

    A priority load is a load that the design assigns to the generator set when the normal supply is lost. A good design divides loads into classes for life safety (emergency lighting, fire pumps, stair pressurization fans, firefighting lifts), operational criticality (the reservation server, card locks, clean water and wastewater pumps, food cold rooms), and comfort (ballroom air conditioning, laundry, decorative lighting). The list of loads on the generator panel is a design fact that must be known before an outage. The opening case shows the consequence when the transfer pump is not on the list. The technician does not move circuits to the generator panel; they record the gap for the chief engineer.

    Generator capacity is stated in kVA, while loads are often in kW:

    Pg=Sg×cos⁡φP_g = S_g \times \cos\varphi

    where PgP_g is the generator’s active power (kW), SgS_g the rated apparent power (kVA), and cos⁡φ\cos\varphi the rated power factor, generally 0.8. The sum of running loads ∑Pi\sum P_i must not exceed PgP_g, with a margin for motor starting current (Chapter 36).

    Load shedding is the automatic or planned disconnection of less important loads so that the generator set is not overloaded. A United States military facility document on generator sets includes a load shed plan in the operation of the generator system, and asks that the sequence of operation upon loss of normal power define load shedding, the motor starting sequence, and the method of return to normal power with its time delays.

    A motor that starts turning draws a current far above its running current. The same document notes that motor starting current can be as much as six times the running current and can lower the generator’s voltage and frequency even when the generator set is large enough for the running load. The running apparent power of a motor is:

    Srun=Pη×cos⁡φS_{run} = \frac{P}{\eta \times \cos\varphi}

    where PP is the motor’s rated power (kW), η\eta the efficiency, and cos⁡φ\cos\varphi the motor power factor. Starting power is estimated as Sstart≈k×SrunS_{start} \approx k \times S_{run}, with kk up to about 6 for direct-on-line starting; star-delta starters, soft starters, and VFDs reduce it.

    Step loading is adding load to the generator set in several time-spaced steps so that voltage and frequency excursions stay within limits. Small generator sets usually have a single transfer switch, so all loads come on together, whereas larger systems can have several transfer switches to bring loads on in stages. When several motors draw starting current at the same time, the loads need to be sequenced onto the generator set, with time delays on less critical loads so that the most important loads are connected first. A generator set that seems to have “20 percent left” cannot necessarily take one more large pump; adding load outside the plan is a decision for the chief engineer together with the generator contractor.

    How long the generator set can run is estimated from fuel, t=Vfuel/qt = V_{fuel}/q, where VfuelV_{fuel} is the usable volume of diesel (liters) and qq the consumption at the present load (liters per hour) from the generator data sheet. Tanks and fuel quality are covered in Chapter 23 · Fluids & Thermal.

    People trapped in lifts

    Lifts stop in a power outage because their brakes engage when voltage is lost. Some lifts have a device that brings the car to the nearest floor, and some are fed by the generator set; their behavior is set by the design and the lift contractor. Chapter 25 · Buildings & Facilities covers receiving the alarm, the questions to ask before calling the contractor, and the principles of rescue.

    The building technician’s task is limited. They make sure every car is checked through the lift alarm panel, intercom, or cameras. For a car with people inside, they keep up communication, record the time and location, and call the lift contractor or a person trained to rescue passengers, as well as firefighters and medical staff if a passenger is unwell or there is smoke. The technician does not open landing doors or car doors, does not enter the machine room, and does not move the car. When power returns, a lift with people inside can move on its own, so communication is maintained until the lift contractor declares all cars safe.

    Pumps, tanks, and water

    In a rooftop tank system, the transfer pump fills the tank and water flows down to the taps by gravity, so water keeps flowing until the tank is empty. In a booster pump system with a pressure tank, pressure is lost as soon as the pump stops (Chapter 5 · Buildings & Facilities and Chapter 9 · Buildings & Facilities). The reserve time of a rooftop tank:

    twater=VstoredQuset_{water} = \frac{V_{stored}}{Q_{use}}

    where VstoredV_{stored} is the volume of water in the tank when the outage starts (m³) and QuseQ_{use} the average consumption at that hour (m³/h).

    Pipes that lose pressure can draw water back from cross-connections, so backflow prevention in Chapter 11 · Buildings & Facilities matters after a long outage. CDC notes that during a power outage water purification systems may not be functioning fully, so water for drinking, cooking, and hygiene should be bottled, boiled, or treated water, following the advice of the local health department. The wastewater pumps in the basement sump also stop, and an outage during heavy rain can make the sump overflow (Chapter 39 · Water & Water Treatment). When power returns, pumps whose tanks are empty are not left to run dry; the plumbing technician checks levels first.

    Food and medicines that must stay cold

    CDC guidance for United States households states that if the doors stay closed, food stays safe up to 4 hours in a refrigerator, 48 hours in a full freezer, and 24 hours in a half-full freezer; the refrigerator should be at 40 °F (about 4 °C) or below. Thawed frozen food that still contains ice crystals or is still at 40 °F or below can be refrozen or cooked, and food is never tasted to judge whether it is safe.

    For a hotel kitchen, those figures are only a rough comparison; the decision to discard or use food is made by the head chef according to the food safety system and temperature records. For the technician: cold room doors stay closed, the time of the outage is recorded, and the temperature is read before the door is opened (Chapter 21 · Fluids & Thermal). CDC advises that medicines that must be kept refrigerated be discarded when the power has been out for a day or more, unless the label says otherwise; that decision belongs to health staff.

    Staged restoration when power returns

    Cold load pickup is the surge in load when the supply returns after a long outage, because equipment that normally cycles in turn now comes on together: every thermostat calls for cooling and every pump tries to fill its tank. Switching on all breakers at once can exceed the main protective device setting, as in the opening case.

    Retransfer is the transfer of load from the generator set back to the normal supply by the transfer switch after the normal supply has been restored. An automatic transfer switch can coordinate the whole sequence: starting the generator set, transferring the load, retransferring, and then shutting down the generator set. The retransfer time delay and the generator cool-down are set by the designer and the contractor; the technician does not change them.

    Motors give a reason to wait. An induction motor disconnected from its source keeps generating residual voltage until its residual magnetism dies away. According to a United States military electrical working group guide, motor voltage should fall below 0.25 per unit before connection to another source; that decay takes only 1 to 2 seconds, but transfer should be delayed 5 to 10 seconds to be safe for several motors at once. Connecting a motor that is still turning to a source that is not synchronized can damage windings, insulation, or couplings.

    Loads that the transfer switch does not control are restored in a written sequence approved by the chief engineer, for example: water and wastewater pumps after levels are checked, servers and card locks after the UPS reports a stable supply, the kitchen and cold rooms, air conditioning zone by zone, and last, large non-priority loads such as the laundry. Each step is given a pause until current and voltage are stable. Chillers are started according to the manufacturer’s procedure by their operator or contractor.

    Afterwards the technician checks what is often left behind: lifts in a special mode, faults on the alarm panel and the building management system, timers, pumps that did not restart automatically, and cold rooms whose temperature has not yet come down. The generator set goes back to automatic mode and its day tank is refilled according to Chapter 23 · Fluids & Thermal.

    Records and review

    The incident record contains the time of the outage, the time the generator set was ready and the load transferred, the loads that came on and those that did not, alarms, people trapped and the time they got out, the time utility power returned, the time of retransfer, the time all loads were restored, fuel used, and cold room temperatures. All times use one reference, for example the building management system clock, so that the sequence of events can be reconstructed. From it the technician works out how long the generator set carried the load, how long non-priority loads were off, and how long the cold rooms were without power. The review asks which loads should have been on the generator circuit, which restoration sequence needs rewriting, and which drills need repeating (Chapter 12 · Safety).

    The division of authority is also written down. Permenaker 12/2015 (Minister of Manpower Regulation) on electrical safety and health in the workplace sets out that planning, installation, alteration, and maintenance of electrical installations are carried out by an Ahli K3 bidang listrik at the company or at a PJK3 (an occupational safety and health service company), that installation and maintenance may be carried out by a Teknisi K3 listrik (certified electrical technician), and that a company with electrical generation of more than 200 kVA must have an Ahli K3 bidang listrik. As of November 2026 the JDIH Kemnaker lists this regulation as in force; Permenaker 11/2026 revoked some of its provisions without changing the articles on who carries out the work. A hotel with a generator set above 200 kVA therefore has a person responsible for electrical decisions during an outage, and their name is written in the emergency response plan.

    Worked example

    The figures in the examples below are practice figures, unless their origin is stated.

    Example 1: do the priority loads fit on the generator set. A 500 kVA generator set with a power factor of 0.8 gives Pg=500×0.8=400P_g = 500 \times 0.8 = 400 kW. Loads on the generator panel: lighting and emergency lighting 40 kW, two lifts 44 kW, transfer pump 15 kW, booster pump 11 kW, wastewater pump 7.5 kW, servers and UPS 20 kW, kitchen ventilation and refrigeration 60 kW, so ∑P=197.5\sum P = 197.5 kW. If the 180 kW ballroom air conditioning is added, the total is 197.5+180=377.5197.5 + 180 = 377.5 kW, that is, 377.5/400=94377.5/400 = 94 percent of capacity. The remaining 22.5 kW is too small for pump starting current (Example 2), so the ballroom air conditioning belongs in the class shed first.

    Example 2: three pumps starting together. With η=0.9\eta = 0.9 and cos⁡φ=0.85\cos\varphi = 0.85, the denominator is 0.9×0.85=0.7650.9 \times 0.85 = 0.765. Transfer pump 15 kW: Srun=15/0.765=19.6S_{run} = 15/0.765 = 19.6 kVA, and with k=6k = 6, Sstart=6×19.6=117.6S_{start} = 6 \times 19.6 = 117.6 kVA. Booster pump 11 kW: 11/0.765=14.411/0.765 = 14.4 kVA, starting 86.3 kVA. Wastewater pump 7.5 kW: 7.5/0.765=9.87.5/0.765 = 9.8 kVA, starting 58.8 kVA. If all three start at once, the surge is 117.6+86.3+58.8=262.7117.6 + 86.3 + 58.8 = 262.7 kVA, that is, 262.7/500=53262.7/500 = 53 percent of the generator rating. The practice generator data sheet gives the largest accepted load step as 40 percent, that is, 200 kVA. Simultaneous starting exceeds it; sequential starting with a largest step of 117.6 kVA does not.

    Example 3: how long the rooftop tank lasts. A 40 m³ rooftop tank is 70 percent full when the outage starts, that is, 0.7×40=280.7 \times 40 = 28 m³. Evening consumption of 14 m³/h gives twater=28/14=2t_{water} = 28/14 = 2 hours. A 45-minute outage uses 14×0.75=10.514 \times 0.75 = 10.5 m³ and leaves 28−10.5=17.528 - 10.5 = 17.5 m³, that is, 17.5/40=43.7517.5/40 = 43.75 percent of the tank. If the outage lasts 3 hours, the upper floors run dry after 2 hours, unless the transfer pump is on the generator circuit.

    Example 4: how long the diesel lasts. A 1,000 L day tank is 80 percent full, that is, 800 L. The practice generator data sheet gives a consumption of 85 L/h at 75 percent load, so t=800/85=9.4t = 800/85 = 9.4 hours before the day tank needs refilling from the storage tank. This figure only holds if the fuel transfer pump works and the fuel is clean (Chapter 23 · Fluids & Thermal).

    Example 5: cold load pickup and staged restoration. Before the outage, the building load is 900 kW: 400 kW without air conditioning and 500 kW of air conditioning that normally runs at an average of 70 percent of its connected capacity, that is, 500/0.7=714500/0.7 = 714 kW. After a 45-minute outage on a hot night, every unit calls for cooling, so if all breakers are switched on together the momentary load is roughly 400+714=1,114400 + 714 = 1{,}114 kW, not counting starting current. The practice main protective device is set for 1,000 kW, so that surge is 1,114−1,000=1141{,}114 - 1{,}000 = 114 kW above it. If the load is restored in five steps, for example 250, 150, 240, 240, and 234 kW, the largest step is only 250 kW, and each step comes on after the previous one is stable.

    Example 6: reading the incident record. The record shows the outage at 20:52:10, the generator set ready and the transfer switch moving the load at 20:52:24, PLN power returning at 21:37, retransfer at 21:42, and all loads restored at 22:05. The priority loads were off for 24−10=1424 - 10 = 14 seconds. The generator set carried the load from 20:52 to 21:42, that is, 50 minutes, and at 85 L/h used about 85×50/60=70.885 \times 50/60 = 70.8 L. The cold room that is not on the generator circuit was off from 20:52 to 22:05, that is, 73 minutes, well under the 4 hours in the CDC guidance for a closed refrigerator; the head chef still reads its temperature before using the contents.

    Stop conditions

    1. The main breaker, the building’s switchgear breaker, or the main panel breaker is open with a relay flag dropped, a burning smell, smoke, noise, or water nearby: do not reclose it and do not open the compartment; keep people away and hand over to an Ahli K3 bidang listrik or authorized electrician, and for the medium-voltage side to PLN staff or an authorized person according to Chapter 110.
    2. People are trapped in a lift: do not open landing doors or car doors, do not enter the machine room, and do not move the car; keep up communication and call the lift contractor or a person trained to rescue passengers, as well as firefighters and medical staff if a passenger is unwell or there is smoke, according to Chapter 25 · Buildings & Facilities.
    3. The generator set fails to start, stops, shows an alarm, smokes, or leaks diesel: do not reset it repeatedly and do not force it to run; report to the chief engineer and call the generator contractor according to Chapter 36 and Chapter 23 · Fluids & Thermal.
    4. The transfer switch does not transfer the load or does not retransfer: do not operate it manually, through a bypass, or by changing settings; hand over to an Ahli K3 bidang listrik or the transfer switch contractor.
    5. There is a request to connect a portable generator set to a fixed panel, or a portable generator set is running inside the building, in a basement or garage, or near windows and vents: stop; carbon monoxide and backfeed can kill, and connecting a generator set belongs to an authorized electrician according to Chapter 36 and the R22 chapter on temporary power for events and exhibitions (Chapter 117).
    6. There is a request to work on a panel or circuit “while the power is off”: refuse; the circuit is treated as live until it has been isolated, locked off, and proved dead by an authorized person according to Chapter 76.
    7. The kitchen hood exhaust fan has stopped while gas equipment is still lit: ask the head chef to shut down the gas equipment according to the kitchen procedure and report to the duty manager.
    8. A water tank is empty, a pump sounds dry, or the basement wastewater sump is rising toward its overflow level: do not run pumps without water and do not enter the sump; report to the plumbing technician and the chief engineer according to Chapter 9 · Buildings & Facilities and Chapter 39 · Water & Water Treatment.
    9. In a hospital, a patient who depends on equipment is in a room without supply: report immediately to the hospital emergency response team; the decision to move the patient or the supply belongs to that team according to Chapter 31 · Buildings & Facilities.

    Common misinterpretations

    Guess what’s wrong first, then open the explanation.

    Common misconception

    The power is off, so it is safe to work on the panel.

    Why is it wrong?

    The generator set, the transfer switch, and utility power can restore voltage at any moment. Panels are worked on only after they have been isolated, locked off, and proved dead.

    Common misconception

    If the generator set is running, everything the building needs is safe.

    Why is it wrong?

    The generator set feeds only the loads connected to its panel. Water pumps, cold rooms, or other systems that are not on the list stay off, as in the opening case.

    Common misconception

    The generator set still has 20 percent left, so a large pump can be added.

    Why is it wrong?

    Motor starting current can be as much as six times the running current. Spare capacity at running load is not necessarily enough for a starting step.

    Common misconception

    As soon as PLN power is back, switch on every breaker so that guests are comfortable quickly.

    Why is it wrong?

    After a long outage, cold load pickup and simultaneous starting currents can exceed the main protective device setting. Staged restoration is faster than a second blackout.

    Common misconception

    A quick-thinking technician may open the lift door to get the guests out.

    Why is it wrong?

    Passenger rescue is work for trained persons with a specific procedure. The building technician keeps up communication and calls them.

    Chapter 36 on generator sets and transfer switches gives the basis for generator capacity and backfeed prevention, Chapter 107 on UPS explains the loads that stay on before the generator set is ready, and Chapter 25 · Buildings & Facilities on lift emergency response is the main reference for people who are trapped. For water, see Chapter 5 · Buildings & Facilities, Chapter 9 · Buildings & Facilities, and Chapter 11 · Buildings & Facilities; for fuel Chapter 23 · Fluids & Thermal; for hospitals Chapter 31 · Buildings & Facilities; and for incident review Chapter 12 · Safety.

    Exercises and worked solutions

    The figures in the exercises are for practice.

    Try to answer first, then open the worked solution.

    1. A 250 kVA generator set with a power factor of 0.8 feeds 185 kW of priority loads. What percentage of its capacity is used, and what does that mean for an 11 kW pump that someone wants to add?

      Check my answer
      See the worked solution

      The generator’s active power is 250×0.8=200250 \times 0.8 = 200 kW, so the load is 185/200=92.5185/200 = 92.5 percent. The remaining 15 kW is about the same as the pump’s running load and far below its starting power, so the pump may be added only if other loads are shed according to the load shed plan.

    2. The hotel’s switchgear breaker is open with a relay flag dropped, while the neighboring building is lit. The manager asks for the breaker to be closed. What is the technician’s answer?

      Check my answer
      See the worked solution

      A lit neighboring building and a dropped relay flag point to a fault on the hotel side, not a utility outage. The technician refuses to close the breaker, keeps people away, and calls an Ahli K3 bidang listrik or an authorized medium-voltage person, because closing a breaker onto a fault that has not been found can strike an arc.

    3. A 20 m³ rooftop tank is half full when the outage starts, and consumption is 8 m³/h. How long will the water last?

      Check my answer
      See the worked solution

      The contents are 0.5×20=100.5 \times 20 = 10 m³, so twater=10/8=1.25t_{water} = 10/8 = 1.25 hours, about 75 minutes. If the outage is expected to last longer, guests are informed early and the chief engineer decides whether other loads can be shed so that the transfer pump can be fed by the generator set.

    4. A 22 kW pump with an efficiency of 0.9 and a power factor of 0.85 is started direct on line. Estimate its starting power with a factor of 6.

      Check my answer
      See the worked solution

      Its running apparent power is 22/(0.9×0.85)=22/0.765=28.7622/(0.9 \times 0.85) = 22/0.765 = 28.76 kVA, so its starting power is about 6×28.76=172.56 \times 28.76 = 172.5 kVA. That is why a large pump comes onto the generator set in a step of its own.

    5. A half-full freezer room has been without power for 30 hours because the generator set failed. What can the technician say?

      Check my answer
      See the worked solution

      CDC guidance for United States households gives 24 hours for a half-full freezer that stays closed, and 30 hours is past that. The technician does not decide the fate of the food; they report the length of the outage and the temperatures read to the head chef, who decides according to the hotel’s food safety system.

    6. Event staff want to run a portable generator set in a basement corridor to power the ballroom sound system during the outage. What is wrong?

      Check my answer
      See the worked solution

      A generator set in a basement corridor lets carbon monoxide build up, and CDC asks that generators not be run in a basement or less than 20 feet from any window, door, or vent. If that generator set were connected to a fixed panel without a transfer switch, there would also be a backfeed hazard, so the request is refused and handed over to an authorized electrician according to Chapter 36 and Chapter 117.

    References

    External sources

    • Peraturan Menteri Ketenagakerjaan Republik Indonesia Nomor 12 Tahun 2015 tentang Keselamatan dan Kesehatan Kerja Listrik di Tempat Kerjajdih.kemnaker.go.id
    • Electricity at work: Safe working practices (HSG85, third edition)hse.gov.uk
    • TSEWG TP-9: Automatic Transfer Equipmentwbdg.org
    • UFC 3-540-01 Engine-Driven Generator Systems for Prime and Standby Power Applications, Change 3wbdg.org
    • Keep Food Safe After a Disaster or Emergencycdc.gov
    • What to Do to Protect Yourself During a Power Outagecdc.gov

    Revision history

    DateVersionChange
    November 15, 20261First published

    How to cite

    Kurnia (2026). Total building blackout and recovery: first response, generator sets and priority loads, people trapped in lifts, pumps and water, staged restoration, and records and review. ARSTEMA Academy. Revised November 15, 2026. arstema.com/en/academy/konsep/pemadaman-listrik-total-gedung-dan-pemulihannya-tanggap-pertama-genset-dan-beban-prioritas-orang-terjebak-lift-pompa-dan-air-pemulihan-bertahap-serta-catatan-dan-evaluasi

    Self-check · 3 questions

    Check your understanding before moving on

    Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.

    0/3rated

    Safety limits still apply. This quiz tests reasoning; it doesn’t authorize mixing, adjusting, dismantling, live measurement, or field action.

    1

    A 250 kVA generator set with a power factor of 0.8 feeds 185 kW of priority loads. What percentage of its capacity is used, and what does that mean for an 11 kW pump that someone wants to add?

    2

    The hotel’s switchgear breaker is open with a relay flag dropped, while the neighboring building is lit. The manager asks for the breaker to be closed. What is the technician’s answer?

    3

    A 20 m³ rooftop tank is half full when the outage starts, and consumption is 8 m³/h. How long will the water last?