By Kurnia · Published November 14, 2026 · Version 1 · 19 min read
UPS in buildings
topologies and operating modes, batteries and backup time, bypass, server and critical loads, periodic maintenance, battery hazards, and the limits of technician work
The PLN utility supply at a hotel fails at 02:10, the generator set fails to start on the first attempt, and the 10 kVA UPS that supplies the reservation server, the key card system, the telephone exchange, and the network switches shuts down after four minutes, although the handover documents state about nine minutes. This chapter covers building UPS units from the technician’s side: the role of the UPS between the utility supply and the generator set, standby, line-interactive, and double-conversion topologies, eco mode, lead-acid and lithium batteries, an energy model for estimating backup time, static bypass and maintenance bypass, server and critical loads, redundancy and efficiency, periodic maintenance and records, and battery hazards: hydrogen gas, electrolyte, short circuits and DC arcs, and lithium thermal runaway. It draws on technical documents from United States and United Kingdom agencies and on Permenaker 12/2015. Opening the UPS, working on battery racks, operating the manual bypass, and disconnecting batteries are stated to be work for UPS technicians or authorized vendors.
This material involves real hazards. A concept explanation doesn’t replace site procedures, competency, energy isolation, the latest SDS, or a work permit.
At 02:10 the PLN utility supply to a 180-room hotel fails. The generator set fails to start on the first attempt, so the only source of power for the reservation server, the guest room key card system, the telephone exchange, and the network switches is the 10 kVA UPS in the server room. The handover documents state a backup time of about nine minutes at the connected load. That night the UPS beeps, shows a low battery warning, and shuts down after four minutes, two minutes before the generator set is finally started. The front office opens rooms with the master key and registers guests by hand.
The next morning two things are found: the UPS batteries are six years old and have never had a capacity test, and the split air conditioner in the server room has been dead for three weeks, so the room sits at about 34 °C. The nine-minute figure belongs to new batteries at the design temperature. The duty technician operated nothing incorrectly; what was missing was the understanding that backup time changes with age, temperature, and load, and the records that would have shown that change before the outage.
Scope
This chapter covers static UPS units in buildings from the building technician’s side: function and topology, operating modes on the display, batteries and estimated backup time, bypass, loads suitable for a UPS, maintenance that can be observed and recorded, and battery hazards. It is learning material, not a work instruction. Paid UPS and battery standards, such as IEC 62040 and the IEEE battery standards series, are only named.
Generator sets and transfer switches are covered in Chapter 36 on generator sets, transfer switches, and standby supply, surge protection in Chapter 35, isolation and disconnection in Chapter 31, and work permits in Chapter 76 on safe work. Batteries from the vehicle side are in Chapter 7 · Automotive & Electric Mobility on traction batteries and charging, non-sinusoidal UPS currents in Chapter 10 on harmonics, redundancy in Chapter 10 · Systems, Diagrams & Diagnosis on reliability and MTBF, and the alternative supply for medical rooms in Chapter 102 on electrical systems in medical rooms.
Work outside the building technician’s authority: opening the UPS cover or the battery cabinet, working on an energized battery rack, measuring inside the UPS, operating the manual maintenance bypass, disconnecting or connecting batteries, replacing battery blocks, changing UPS settings, and clearing alarms that have not been investigated. That work belongs to UPS technicians from the manufacturer or an authorized distributor, or to electrical OHS personnel appointed under Permenaker 12/2015. The building technician reads the display, records, keeps the room cool, ventilated, and clean, and reports.
Why critical loads need a UPS
A static uninterruptible power supply is an electronic device that stores energy in batteries and delivers it to the load without a break when the incoming supply is disturbed. Technical paper TSEWG TP-19 from the United States military electrical working group states that a UPS conditions incoming power and provides ride-through power for short outages; for long outages a generator set is needed, and the UPS supplies the load while the generator set is brought on line. A UPS is therefore a bridge, not a replacement for a generator set.
A generator set needs time to start and reach stable voltage and frequency before the transfer switch moves the load (Chapter 36). Lamps and pumps can wait a few seconds; information technology equipment cannot. IT equipment power supplies are designed to store energy for only about 20 milliseconds when the supply is interrupted, which is called the hold-up time. A longer disturbance makes servers and switches shut down and restart, and data being written can be corrupted.
Because part of the power entering a UPS is always lost as heat, the first design step is to decide which equipment actually needs one. In a hotel this is usually the reservation server, the key card system, the core switches, and the telephone exchange.
UPS topologies and operating modes
TP-19 distinguishes three basic topologies.
- A standby UPS lets the load run from the PLN utility supply until the UPS detects a disturbance, then switches to battery.
- A line-interactive UPS boosts or bucks the incoming voltage before passing it to the load, or uses the battery.
- A double-conversion UPS isolates the load from the incoming supply: alternating current is rectified, then converted back to alternating current by the inverter.
A double-conversion UPS consists of a rectifier that also charges the battery, an inverter, the battery, and a static bypass switch. The load is always supplied by the inverter, so the change to battery does not interrupt current. The same guide rates double conversion excellent in reliability and disturbance suppression, but only fair in input power quality and efficiency; a standby UPS is the reverse. The data center guide of the United States Department of Energy calls double conversion the most common system in data centers, with efficiency that rose from 85 to 90 percent in the 1990s to 95 percent or higher in 2023.
Some double-conversion units have an eco mode whose efficiency can reach 99 percent. This mode usually bypasses the double conversion so that the load is supplied by building power; when the utility supply fails there is a transfer time to battery of about 1 to 3 milliseconds, and with a transformer that time can be four times longer, which is not recommended for IT loads. A UPS used to filter incoming power should therefore not be run in eco mode.
The UPS display shows the operating mode: normal or online, battery, bypass, or eco. The technician always asks: where is the load being supplied from, and is that what is expected?
UPS batteries: types, life, and temperature
The lead-acid battery is the most common large-capacity rechargeable battery and is used in the UPS of computer, communication, and control systems. A vented battery lets the hydrogen and oxygen from charging escape to the air and needs periodic topping up with water. A VRLA battery (valve-regulated lead-acid) recombines that gas into water so it needs no topping up, but it still has a pressure relief valve.
United States military facility criteria prefer vented batteries for UPS use and restrict VRLA because its life is shorter and it tends to fail without warning. VRLA is allowed for small spaces or places that must not be exposed to electrolyte leakage, including many UPS rooms, but it is prohibited in environments with uncontrolled temperature and in places that are seldom checked, because it can fail within only a few years. For life-cycle cost comparisons, the criteria use a life of 3 years for small VRLA, 7 years for large VRLA, 10 years for small vented batteries, and 15 years for large vented batteries. These figures are for cost calculations; replacement schedules are set from test results and manufacturer recommendations.
Temperature speeds up aging. The electrical safety handbook of the United States Department of Energy gives the optimum temperature for maximum lead-acid battery life as 25 °C ± 1 °C, and notes that VRLA is more sensitive to high temperature and more vulnerable to thermal runaway during abusive charging. A UPS room at 34 °C, as in the opening case, runs well above that temperature every day.
Thermal runaway is uncontrollable self-heating of an electrochemical system. In a lithium battery, a cell undergoing it rapidly releases toxic and flammable gas and can become an ignition source for the cells around it. United States military facility criteria prohibit lithium-based batteries for stationary use in occupied buildings, noting that there are no industry standards yet for stationary lithium batteries. That rule applies to United States military facilities; in other buildings, lithium UPS batteries follow the design, permits, and manufacturer instructions.
Backup time: estimating with an energy model
Backup time is how long the UPS can supply the load from the battery until the battery voltage reaches its end limit. The actual figure is read from the battery manufacturer’s discharge tables, and the battery size is set by the designer according to sizing standards, for example IEEE 1184 for UPS applications. A simple model still helps the technician understand why the handover figure changes.
A UPS is rated in kVA and kW. The real power of the load is
where is real power (W), is apparent power (VA), and PF is the power factor. The load fraction is divided by the kW rating of the UPS. The energy model for backup time:
where is the backup time (minutes), the nominal battery string voltage (V), the rated capacity (Ah), the fraction of capacity that can actually be drawn at the present discharge rate, temperature, and age (0 to 1), the inverter efficiency (dimensionless), and the real power of the load (W). The factor 60 converts hours to minutes.
The assumptions: the load power is constant, is taken from manufacturer data, and the battery starts fully charged. A battery drained within ten-odd minutes delivers far less than its rated capacity, so is well below 1, and an old or hot battery lowers it further. The model is only for estimates; whether a battery is adequate is decided by a capacity test by the vendor. The lesson: every added load shortens the backup time, and a falling only shows up through recorded periodic tests.
Static bypass and maintenance bypass
The static bypass switch is there in case part of the UPS fails: power is routed around the UPS module so that the load stays supplied, and TP-19 calls it a second line of defense. The UPS also goes to bypass on overload or overheating.
An external maintenance bypass is a breaker panel outside the UPS that allows the UPS to be taken out of service while the load stays supplied. TP-19 strongly recommends it; its breakers are arranged with an interlock, typically a key system, so that the transfer is make-before-break through the static bypass inside the UPS. That sequence is a vendor procedure; one wrong step can drop the critical load.
What the building technician needs to understand is what the bypass state means. While the load is on bypass, it is supplied directly from building power, so impulses can reach the load, and if the incoming supply fails, the load fails too because the inverter and battery are not supplying it. The word “bypass” on the display is not a sign of safety but an unprotected state that is recorded, reported, and ended by the vendor as soon as possible.
The UPS and the generator set also need to be coordinated by the designer. The frequency of a generator set that has just started can fluctuate, and the UPS will reject the generator as a source and stay on battery until the frequency is stable; the generator set must also be able to supply the load while the UPS is on bypass. The planned backup time therefore includes the time spent waiting for the generator frequency to stabilize.
Server loads, critical equipment, redundancy, and efficiency
TP-19 names the loads that cause a UPS the most trouble as motors, transformers, electric discharge lighting, thyristor rectifiers, and magnetic amplifier power supplies, because of their nonlinearity or inrush current. New loads are therefore not plugged into UPS outlets without the engineer’s approval.
N+1 redundancy is an arrangement with one unit more than the load requires, so that one unit can fail or be maintained without dropping the load. The Department of Energy guide warns that a large UPS paralleled with an identical standby unit operates at a load fraction of at most 50 percent; two N+1 units each working at 30 percent will work at 40 percent if the same load is served by three smaller units, and that increase can raise efficiency by 1.2 percent.
Efficiency also determines heat. The UPS loss is
where is the load power (W) and the efficiency at that load fraction. This loss becomes heat that the room air conditioner must remove, so an efficient UPS saves energy in the UPS and in the cooling.
A list of UPS loads should be posted near the UPS: load name, outlet or branch panel, measured power, and owner. During a long outage, the list shows which loads may be shed; shutting servers down in an orderly way is the IT manager’s task.
Periodic maintenance, records, and limits of work
Opening the UPS or the battery cabinet, measuring cell voltages, tightening connections, testing capacity with a real discharge, and replacing components are done by UPS technicians or the vendor according to the standards the manufacturer refers to, for example IEEE 450 for vented batteries and IEEE 1188 for VRLA. The building technician observes from outside, records, and looks after the room:
- The operating mode on the display is normal or online, not bypass or battery, unless there is recorded vendor work.
- Alarms and the event history are recorded as they are, not cleared.
- The load fraction on the display is compared with earlier records.
- Temperature of the UPS room and battery room, and the air conditioning and ventilation working.
- The battery cabinet from outside: no unusual smell, leaks, or heat felt from the door.
- The room is clean, not used as a store, and the way to the UPS is not blocked.
The Department of Energy handbook asks that battery connections be kept clean and tight, that connections not be repaired while current is flowing, and that battery hazards and first aid information be clearly posted near the equipment. HSE asks that the working life of each battery be recorded, for example installation date and charging performance. The UPS logbook holds the battery installation date, capacity test results, daily room temperature, alarms, and load changes.
Permenaker 12/2015 (Minister of Manpower Regulation) on electrical OHS in the workplace applies to activities operating at more than 50 volts alternating current or 120 volts direct current, and states that maintenance is carried out by an Electrical OHS Expert, while installation and maintenance can be carried out by an Electrical OHS Technician, in the company or in an OHS service company. As of November 2026, JDIH Kemnaker lists its status as in force. The battery string in Example 2 is at 192 volts direct current, so work on a string like that falls within the scope of that regulation.
Battery hazards
The Department of Energy handbook lists the hazards of stationary batteries: accidental grounding of one polarity, DC arcing from a short circuit across terminals or cables, hydrogen that can burn, explode, and poison, electric shock from exposed terminals, batteries that explode if shorted or charged too fast, and electrolyte that burns the skin. Batteries are considered a live source and are placed in an area accessible only to authorized persons.
Hydrogen. Batteries produce hydrogen and oxygen when charged, faster as they approach full charge, and a small spark is enough to ignite the mixture. Mixtures of air with 4 percent hydrogen (lower explosion limit) to 75 percent (upper explosion limit) ignite readily, and HSE recommends a concentration of no more than 0.4 percent by volume, that is 10 percent of the lower limit, in rooms that people enter, and 1 percent by volume in enclosures that people do not enter. Hydrogen rises and collects at the ceiling, so air inlets are placed low and outlets high. For natural ventilation with an air velocity of at least 0.1 m/s, HSE gives the minimum area of each opening as
where is the area (cm²), the number of cells, the overcharging current (A), and the dilution factor: 10 for workrooms and 4 for closed enclosures. HSE also treats a zone 1 hazardous area as extending up to one meter in all directions around batteries under charge. The formula is for reading a design; designing ventilation is engineering work. VRLA releases hydrogen far less often, but charging too fast or too long can raise the pressure until its valves open.
Short circuits and DC arcs. Terminals short-circuited by an uninsulated wrench or screwdriver release energy very quickly; the metal heats up, can explode into a shower of molten metal, and the sparks give off ultraviolet light that damages the eyes. HSE notes that many explosions happen when batteries are being connected or disconnected, and that some large batteries are above 120 volts DC. Disconnecting and connecting UPS batteries is therefore never building technician work.
Electrolyte. Sulfuric acid or potassium hydroxide is highly corrosive, can permanently damage the eyes, and is poisonous if swallowed. Safety showers and eyewash stations are provided near batteries. Chemicals and safety data sheets are covered in Chapter 6 · Safety.
Lithium. Its particular hazards are thermal runaway as an event initiator or propagator, delayed re-ignition up to days later, and explosive or poisonous gases; water-based suppression may be insufficient, and thermal runaway can continue after a gaseous suppression system has put out the fire. A lithium battery cabinet that is smoking or hot is therefore not approached, the building is evacuated according to the fire procedure (Chapter 17 · Buildings & Facilities on fire protection), and the fire service is told the battery type.
Worked example
The figures in the examples below are practice figures unless their origin is stated.
Example 1: UPS load fraction. A 10 kVA UPS with an output power factor of 0.9 has a real power rating of W. The measured load is 6.3 kW, so its load fraction is , that is 70 percent. If staff add a 2 kW water heater to a UPS outlet, the load becomes W or , and the backup time of every other load shortens with it.
Example 2: backup time with new batteries. The string contains 16 blocks of 12 V, 9 Ah, so V. At a discharge rate of ten-odd minutes, the example manufacturer data give , and . With a 6.3 kW load:
This is the nine-minute figure in the handover documents of the opening case.
Example 3: reading an aging battery. That night the UPS lasted only 4 minutes at the same load. With the same model, , and the ratio to a new battery is , that is 44 percent. The model does not separate the effects of age and temperature, but it is enough to ask the vendor for a battery test and to have the room air conditioning repaired.
Example 4: shedding non-critical loads. If 2.1 kW of non-critical load is shed, the load becomes W, and with new batteries minutes. The model assumes a constant , whereas at a lower discharge rate the manufacturer data give a different , so the figure is an estimate.
Example 5: ventilation area according to HSE. HSE’s own example uses four six-cell batteries in a workroom with an overcharging current of 20 A: cm² for the low and the high opening each. For a vented 96-cell UPS string with an overcharging current of 2 A in a workroom, cm², for example an opening of 24 cm by 24 cm. In an enclosure that people do not enter, cm².
Example 6: efficiency and heat. A 6 kW load running all year uses kWh. At 90 percent efficiency the UPS draws kWh, and at 95 percent kWh, a difference of kWh per year. Heat in the UPS room is W against W. The Department of Energy guide uses the same method for a data center using 13,140 MWh per year: its savings are 768,421 kWh.
Stop conditions
- The UPS display shows the load on bypass, the load on battery although the utility supply is present, or a battery, inverter, or rectifier alarm: do not operate the manual bypass and do not clear alarms repeatedly; record, report to the chief engineer, and call the UPS technician or vendor.
- The battery cabinet gives off an unusual smell, smoke, heat felt from outside, leaking liquid, or a battery block looks swollen: do not open the cabinet and do not touch the batteries; keep people away, let the ventilation keep running, and contact the vendor. If there is smoke or fire, follow the building fire procedure and tell the fire service the battery type.
- A lithium battery cabinet or room is smoking, hot, or hissing: leave the room, follow the building fire procedure, and do not go back in until the fire service and the vendor declare it safe, because re-ignition can be delayed by days.
- The hydrogen alarm sounds, the battery room ventilation has stopped, or the ventilation openings are blocked: do not bring any ignition source into that room and do not start any work there; report to the chief engineer, and call the UPS vendor and a ventilation technician.
- The work would require opening the UPS or battery cabinet, measuring inside it, disconnecting or connecting batteries, or replacing battery blocks: stop; that work belongs to UPS technicians or authorized vendors and appointed electrical OHS personnel.
- The UPS room air conditioner has stopped or the room temperature stays above the design temperature: report to the HVAC technician and the chief engineer, and record the temperature; do not cool the UPS by opening its cabinet doors.
- A new load is about to be plugged into the UPS, or the load fraction on the display rises with no recorded cause: postpone adding load until the engineer and vendor have assessed capacity and backup time.
- The outage is long and the backup time is nearly exhausted while the generator set has not picked up the load: tell the IT manager so that servers are shut down in an orderly way according to the load list; the electrical technician does not shut servers down personally and does not bypass the UPS.
Common misinterpretations
Guess what’s wrong first, then open the explanation.
Common misconception
A UPS can replace the generator set during an outage.
Why is it wrong?
A UPS provides ride-through power for short outages and bridges the load until the generator set takes over. Its backup time is a matter of minutes, unless it is specially designed.
Common misconception
Maintenance-free batteries do not need checking.
Why is it wrong?
VRLA batteries need no topping up, but they tend to fail without warning and are more sensitive to heat. Without periodic tests and temperature records, their loss of capacity only shows during an outage.
Common misconception
Bypass on the display means the UPS is safe.
Why is it wrong?
On bypass, the load is supplied directly from building power without the protection of the inverter and battery. If the incoming supply fails at that moment, the load fails too.
Common misconception
The backup time in the handover documents holds for the life of the UPS.
Why is it wrong?
That figure holds for the load, temperature, and batteries at the time of the test. Added load, a hot room, and aging batteries shorten it.
Common misconception
Sealed batteries do not give off gas.
Why is it wrong?
VRLA batteries release hydrogen far less often, but charging too fast or too long can open their valves. A battery room still needs ventilation and must be kept free of ignition sources.
Links to other chapters
Chapter 36 on generator sets and transfer switches explains the other side of the bridge that the UPS builds, and Chapter 102 on electrical systems in medical rooms covers loads that need batteries or a UPS. Backup batteries for other systems are in Chapter 22 · Buildings & Facilities on fire alarm power supplies, Chapter 96 on the hotel telephone exchange, and Chapter 106 on emergency lighting and exit signs. Chapter 108 on hotel data networks covers the switches that are usually supplied by a UPS.
Exercises and worked solutions
The figures in the exercises are for practice.
Try to answer first, then open the worked solution.
A 6 kVA UPS with an output power factor of 0.8 supplies a measured load of 3.6 kW. What is its load fraction, and how much power remains?
Check my answer
See the worked solution
The real power rating is W, so the load fraction is or 75 percent, and the remainder is W. That remainder is not automatically available for use, because every added load shortens the backup time.
A battery string of 20 blocks of 12 V, 7 Ah, , , supplies a 3.6 kW load. Estimate its backup time with the energy model.
Check my answer
See the worked solution
V, and minutes. This figure holds only as long as matches the battery condition; an aging or hot battery gives a shorter time.
The UPS display has shown the load on bypass since the morning, and there is no record of vendor work. What does the duty technician do, and why is that state risky?
Check my answer
See the worked solution
The technician records the time and the display message, does not operate the bypass and does not clear the alarm, then reports to the chief engineer and calls the vendor. On bypass, the load is supplied directly from building power, so impulses can reach the load, and a utility outage immediately drops the load.
A vented battery room holds a 120-cell string with an overcharging current of 1.5 A, and people enter it. What is the minimum area of each ventilation opening by the HSE formula, and where are they placed?
Check my answer
See the worked solution
cm² for each opening. The inlet is placed low and the outlet high, because hydrogen rises and collects at the ceiling.
Why do United States military facility criteria prohibit VRLA in places that are seldom checked, and what does that mean for a hotel?
Check my answer
See the worked solution
VRLA batteries tend to fail without warning within a few years of installation, so a place that is seldom checked only learns of the failure when the battery is needed. For a hotel, a UPS with VRLA batteries needs an observation schedule, temperature records, and capacity tests by the vendor, none of which existed in the opening case.
A hotel wants to run its server room UPS in eco mode all the time. What needs to be considered?
Check my answer
See the worked solution
Eco mode raises efficiency to about 99 percent, but the load is supplied by building power and there is a transfer time of about 1 to 3 milliseconds to battery, longer if a transformer is present. If the UPS is used to filter incoming power or the load contains IT equipment, eco mode is not recommended, and the decision is made by the engineer together with the vendor and the IT manager.
References
External sources
- TSEWG TP-19: Static Uninterruptible Power Supply (UPS)wbdg.org
- Best Practices Guide for Energy-Efficient Data Center Designenergy.gov
- UFC 3-520-01 Interior Electrical Systemswbdg.org
- DOE-HDBK-1092-2013, Electrical Safetyenergy.gov
- Using electric storage batteries safelyhse.gov.uk
- Consideration of Lithium-Ion Battery Hazards in DOE Nuclear Facilitiesenergy.gov
- Peraturan Menteri Ketenagakerjaan Nomor 12 Tahun 2015 tentang Keselamatan Dan Kesehatan Kerja Listrik Di Tempat Kerjajdih.kemnaker.go.id
Revision history
| Date | Version | Change |
|---|---|---|
| November 14, 2026 | 1 | First published |
How to cite
Kurnia (2026). UPS in buildings: topologies and operating modes, batteries and backup time, bypass, server and critical loads, periodic maintenance, battery hazards, and the limits of technician work. ARSTEMA Academy. Revised November 14, 2026. arstema.com/en/academy/konsep/ups-di-gedung-topologi-dan-mode-kerja-baterai-dan-waktu-cadang-bypass-beban-server-dan-alat-kritis-perawatan-berkala-bahaya-baterai-serta-batas-kerja-teknisi
Self-check · 3 questions
Check your understanding before moving on
Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.
Safety limits still apply. This quiz tests reasoning; it doesn’t authorize mixing, adjusting, dismantling, live measurement, or field action.
A 6 kVA UPS with an output power factor of 0.8 supplies a measured load of 3.6 kW. What is its load fraction, and how much power remains?
A battery string of 20 blocks of 12 V, 7 Ah, , , supplies a 3.6 kW load. Estimate its backup time with the energy model.
The UPS display has shown the load on bypass since the morning, and there is no record of vendor work. What does the duty technician do, and why is that state risky?