    Temporary power for events and exhibitions

    portable generators, temporary distribution boards, cables on floors and walkways, RCDs and grounding, weather and water, and dismantling

    A hotel holds a three-day exhibition in its parking area and ballroom foyer with forty stands; the rented generator is placed near the kitchen door, cables cross the guest walkway, an afternoon downpour leaves puddles around the cable connections, and an exhibitor asks for their stand to be connected to a receptacle without an RCD because its RCD keeps tripping. This chapter covers temporary power for events and exhibitions from the building technician’s side: the shock hazard of installations that are put up quickly and used by lay people; power from a building connection point or a portable generator, together with carbon monoxide; temporary distribution boards and sharing the load across phases; cables on floors and walkways, with voltage drop; RCDs and generator grounding; weather and water; and dismantling. It is based on UK HSE guidance on electricity at places of entertainment and on event safety, the CDC page on carbon monoxide, and Permenaker 12/2015. This chapter is learning material: connecting to fixed distribution boards, installing and dismantling boards, connecting generators, live work, and testing RCDs are stated to be work for authorized electrical installers.

    High-risk material

    This material involves real hazards. A concept explanation doesn’t replace site procedures, competency, energy isolation, the latest SDS, or a work permit.

    Section you’re reading: Chapter opening

    A hotel rents out its parking area and ballroom foyer for a three-day food and crafts exhibition with forty stands, some with coffee machines, grills, and refrigerated cabinets. The organizer hires a portable generator and places it near the kitchen loading door so that guests do not see it. Cables from a temporary distribution board run across the guest walkway to the lobby, and on the first afternoon a heavy downpour leaves puddles around cable connections lying on the asphalt. That evening an exhibitor comes to the engineering office: the RCD at their stand keeps tripping, and they ask for the stand to be connected instead to a hotel wall receptacle that “never trips”.

    The building technician did not install that system and must not connect it to the hotel installation, but has to know what makes it dangerous and when a request is refused.

    Scope

    This chapter covers temporary power for events and exhibitions on hotel premises from the building technician’s side: the hazards of temporary installations, power from a building connection point or a portable generator, temporary distribution boards and load sharing, cables on floors and walkways, RCDs and grounding, weather and water, and dismantling. This is learning material, not a work instruction. The chapter contains no steps for connecting cables to fixed distribution boards or to generators, installing or dismantling distribution boards, working on live parts, or testing RCDs.

    Generators, transfer switches, and preventing backfeed are covered in Chapter 36 on generator sets, transfer switches, and standby supply. RCD testing, fault loop impedance, and grounding are in Chapter 18 on grounding tests, fault loop impedance, and RCD testing, RCD types in Chapter 22, inspection of exhibitors’ portable equipment and extension leads in Chapter 114 on inspecting portable electrical equipment in hotels, and installations in wet locations in Chapter 37 on wet and special locations. Neutral current is in Chapter 9, voltage drop in Chapter 28, generator fuel in Chapter 23 · Fluids & Thermal, lightning in Chapter 35, and event audiovisual equipment in Chapter 116 on audiovisual equipment in meeting rooms and ballrooms.

    Outside the building technician’s authority: designing the temporary installation, connecting or disconnecting the supply from hotel boards, connecting generators, installing, opening, and dismantling temporary distribution boards, laying and connecting distribution cables, testing RCDs and grounding, and resetting protective devices after a fault whose cause has not been found. That work belongs to an authorized electrical installer with an Ahli K3 bidang Listrik (electrical safety expert) or Teknisi K3 Listrik (electrical safety technician), and to the generator provider. The building technician shows the power points the hotel provides, checks what is visible from outside, keeps walkways safe, stops dangerous situations by keeping people away, and reports.

    Why temporary power is more dangerous

    A temporary installation is put up within hours, used by lay people, and often located outdoors. GS50, the UK HSE guidance on electricity at places of entertainment, lists the main hazards: electric shock and burns from contact with live parts, exposure to arcing, fire from faulty equipment or installations, separately powered equipment interconnected by a single cable, and explosion when unsuitable equipment ignites flammable vapors or dusts. The guidance regards voltages above 50 V alternating current or 120 V direct current as dangerous even in cool, dry conditions. Permenaker 12/2015 (Minister of Manpower Regulation) uses the same limits for the scope of K3 listrik (occupational electrical safety) at workplaces.

    Electric shock is the result of current flowing through the body. GS50 gives an idea of the magnitudes: about 1 mA can be perceived, 2 mA makes muscles convulse, 50 mA affects breathing, and 100 mA can cause ventricular fibrillation, which is usually fatal; an RCD for personal protection trips at 30 mA. Ohm’s law explains why wet floors and flooded asphalt change the situation:

    Ib=URbI_\text{b} = \frac{U}{R_\text{b}}

    where IbI_\text{b} is the current through the body (A), UU is the touch voltage (V), and RbR_\text{b} is the total resistance of the current path through the body, footwear, and standing surface (Ω). Water lowers RbR_\text{b}, so the same voltage drives a much larger current.

    The second hazard typical of events is visitors who do not know which board is live. For that reason the HSE event safety page asks for electrical equipment to be located, as far as practicable, where members of the public or unauthorized workers cannot touch it.

    Power sources: building connection point or portable generator

    Power for an event comes from two sources. The first is a connection point provided by the hotel installation, for example an industrial receptacle or an event panel permanently installed for that purpose. This point is part of the building installation, and the event installer connects to it under the hotel’s work permit. The second is a rented portable generator, used when building power is insufficient or the location is far away.

    GS50 asks for generators to be maintained, correctly installed, and adequately grounded by a competent person, and if a generator is hired, the organizer has to arrange a competent installer. The guidance also states that it should not be possible to connect generators in parallel with the public supply unless written agreement has been reached with the electricity supplier. For a hotel, this means an event generator is never connected to the building installation through a receptacle or board without a transfer switch designed for it, because its voltage can flow back into the utility network; transfer switches and backfeed are covered in Chapter 36.

    In Indonesia, Permenaker 12/2015 requires employers or managers to implement K3 listrik at the workplace. Planning, installation, modification, and maintenance of installations are carried out by an Ahli K3 bidang Listrik at the company or at a PJK3 (occupational safety service company), and installation and maintenance may be carried out by a Teknisi K3 Listrik; a company that owns electricity generation of more than 200 kVA must have an Ahli K3 bidang Listrik. As of November 2026, JDIH Kemnaker (the Ministry of Manpower legal database) lists the regulation as in force, with the article on who carries out inspection and testing already amended and partly revoked by later regulations. How these articles apply to rented generators and to an exhibition installation lasting a few days is a question for the hotel’s Ahli K3 bidang Listrik and the provincial manpower office.

    Combustion-engine generators produce carbon monoxide, an odorless, colorless gas that can kill without warning. The US CDC asks for generators to be run only outdoors, more than 20 feet from windows, doors, and vents, and never inside a building or garage even with doors and windows open. Twenty feet equals 20×0.3048=6.120 \times 0.3048 = 6.1 m. Kitchen loading doors, fresh-air intakes, and basement car parks are therefore not places for a generator. The common symptoms of poisoning according to the CDC are headache, dizziness, weakness, upset stomach, vomiting, chest pain, and confusion. Basement car park ventilation and carbon monoxide sensors are covered in Chapter 42 · Buildings & Facilities, and generator fuel in Chapter 23 · Fluids & Thermal.

    The HSE event safety page also asks for main electrical intakes and generator enclosures to be located where they are accessible for normal operations and emergencies but segregated from public areas, with danger warning signs around them.

    Temporary distribution boards and power demand

    A temporary distribution board is a board brought by the installer to divide the power from the source among groups of stands, lighting, and other equipment during the event. GS50 asks for connection panels to be locked so that only a responsible person can open them, or interlocked so that they disconnect the power before or as they are opened. A board standing open among visitors is a stop condition.

    Power demand is built up from the list of stands. The installed power of each stand is added up and then multiplied by the demand factor, which is the ratio of the load expected to operate at the same time to the total installed load, chosen by the installer according to the type of event:

    Pd=kd∑Pi,S=Pdcos⁡φP_\text{d} = k_\text{d} \sum P_i, \qquad S = \frac{P_\text{d}}{\cos\varphi}

    where PdP_\text{d} is the demand power (kW), kdk_\text{d} is the demand factor (dimensionless), PiP_i is the installed power of each stand or group (kW), SS is the apparent power the source must provide (kVA), and cos⁡φ\cos\varphi is the average power factor. This apparent power is what is compared with the generator rating; generator sizing against motor starting current, for example from refrigerated cabinet compressors, is covered in Chapter 36. The current per phase on a balanced three-phase supply is I=S/(3 ULL)I = S/(\sqrt{3}\,U_\text{LL}).

    Single-phase stands are divided among the three phases so that their currents are nearly balanced. If they are unbalanced, the neutral conductor carries the difference. For loads with a power factor close to 1, the neutral current can be estimated with

    IN=I12+I22+I32−I1I2−I2I3−I3I1I_\text{N} = \sqrt{I_1^2 + I_2^2 + I_3^2 - I_1 I_2 - I_2 I_3 - I_3 I_1}

    where I1I_1, I2I_2, and I3I_3 are the three phase currents (A). This formula assumes each current is in phase with its own voltage; electronic loads that produce harmonics can make the neutral current larger, as discussed in Chapter 9 on unbalanced loads and neutral current. A broken neutral makes stand voltages swing up and down and can damage equipment.

    GS50 also mentions matters that are the installer’s responsibility and can be recognized from outside. Single-core heavy-current cables must be insulated for the voltage in use and protected against mechanical damage, steel-armored single-core cables are not used because induced currents in the armor make the cable overheat, welding cable is not used because its insulation is inadequate, and connectors for single-core cables must not expose live parts even with the plug withdrawn. Conductors connected to ground or neutral must not have single-pole fuses or switches in them, because their disconnection is not always obvious from equipment failing to work.

    Cables on floors and walkways

    In the UK, slips and trips are the most common cause of injury at work, on average 40 percent of all reported major injuries, and also the most reported injury to members of the public. Cables on the guest walkway make people trip, and cables run over by trolleys or caught in doors have their insulation damaged.

    The HSE event safety page gives guidance on cable routes. Cables are selected and rated for the environment and for adverse weather that may occur. Cables are routed to minimize tripping hazards and mechanical damage, in positions that allow them to be installed and removed safely, and particular care is given to the position of connections. Cable ramps are used where cables cross walkways. Cables should run alongside fence lines, and vehicle routes are segregated from cable routes; where this is not possible, cables are routed by a cable bridge, a supporting catenary, or ramps. For a cable bridge or catenary, HSE advises a height of not less than 5.8 m so that most vehicles can pass beneath, with warning notices in both directions. Buried cables should run in ducts or pipes, and cable joints are not left underground.

    On hotel premises, cable routes also meet evacuation routes, fire doors, and ambulance routes. Cables do not pass under fire doors that must close by themselves, do not cross in front of exit doors without protection, and do not obstruct emergency vehicle routes.

    Long cables to distant stands also reduce the voltage:

    ΔU=2 ρ L IA\Delta U = \frac{2\,\rho\,L\,I}{A}

    where ΔU\Delta U is the voltage drop of a single-phase circuit (V), ρ\rho is the resistivity of copper, about 0.0178 Ω mm2/m0.0178\ \Omega\,\text{mm}^2/\text{m} at 20 °C as in Chapter 18, LL is the one-way cable length (m), II is the current (A), and AA is the cross-sectional area (mm²). The limits are covered in Chapter 28. GS50 also asks for extension leads to be fully unwound from their drums to avoid overheating and for multiple-socket strips to be used instead of stacked adapters.

    RCDs and grounding

    An RCD (residual current device) is a protective device that compares the current entering and leaving a circuit and disconnects the circuit when the difference, which means current leaking to ground, exceeds its rated value. The HSE guidance for entertainers states that RCDs for personal protection are commonly rated 30 mA with a disconnection time of no more than 40 ms, and places the best location for an RCD at the distribution board or at the receptacle. An RCD is a backup layer: good grounding and insulation remain the primary protection.

    GS50 asks for receptacles used by portable equipment to be protected by 30 mA RCDs, for RCDs to be located in readily accessible positions at sub-distribution board level, and notes the UK standard’s recommendation that one 30 mA RCD protects no more than six final circuits. An RCD that trips is a sign of a fault that must not be ignored, and equipment that causes an RCD to trip is taken out of service until the fault is found and put right. RCD plugs or portable adapters are used only when there is no better alternative, because they are easily ignored or bypassed. In the UK, GS50 recommends operating the RCD test button at least once a month and testing the RCD every three months; the method and test instruments are covered in Chapter 18, and the testing is done by a competent person.

    The exhibitor’s request in the opening case is therefore refused. The stand’s RCD trips because there is leakage current from one of its appliances, and moving it to another receptacle does not remove that fault; what is done is to take the faulty appliance out of use and call the installer.

    In systems with a generator, RCDs are installed in tiers. GS50 gives an example: a faulty appliance on a stage receptacle should trip the 30 mA RCD protecting that receptacle, not the 300 mA RCD on the generator output, so the settings of each device are chosen to make discrimination effective; the manufacturer’s advice is also sought before installing an RCD where there is vibration, such as on a generator.

    Generator grounding is the part most often misunderstood. GS50 explains that unless the generator supplies only double-insulated equipment within a few meters of itself, a fault can make an equipment casing live without blowing a fuse or tripping a circuit breaker, so one point of the generator output, usually the neutral or star point, is grounded and bonded to the building’s structural steelwork and to scaffolding carrying electrical equipment. Generators usually have their own means of grounding and do not rely on the grounding of a building installation, their ground resistance must be low enough for fault protection to operate reliably, and it is recommended that the installer who installs the generator test it and record the result. The neutral and grounding of generators are covered in Chapter 36, and grounding in Chapter 29.

    Weather and water

    Tropical afternoon rain is the hardest test for an outdoor installation. The HSE event safety page asks for electrical equipment that could be exposed to rain or other adverse conditions to be constructed or protected with suitable covers, enclosures, or shelters. What is visible from outside is cable connections lying on asphalt or grass, boards standing on low ground where water flows, stand receptacles open to the rain, and cables running through puddles.

    Water lowers the resistance of the current path through the body and the standing surface, as explained at the start, and also creeps into connectors not designed for outdoor use. Degrees of protection against water and dust and requirements for installations in wet locations are covered in Chapter 37 on wet and special locations. The building technician records connectors and boards that look unsuitable for outdoor use.

    The plan for an outdoor event contains weather decisions: who monitors the forecast and the sky, under what conditions outdoor stands and their electrical equipment are shut down, and who asks the installer to disconnect flooded circuits. Lightning and its protection are covered in Chapter 35. Stage frames, tents, and loudspeaker towers are also affected by wind; such structures are covered in Chapter 116 from the suspended-load side.

    Dismantling

    Dismantling is often done in a hurry at night while guests are still passing. The sequence is set by the installer: stand equipment is switched off and unplugged by its owners, circuits are switched off at the temporary distribution board, the source is switched off and declared dead by the installer, and only then are distribution cables coiled and boards moved. Until the installer declares the system dead, every cable and board is treated as live.

    The building technician watches two things. First, disconnection from the hotel connection point is done by the installer who connected it, and the point is returned closed and safe before handover. Second, walkways stay safe while cables are removed, especially if the temporary lighting is switched off as well. GS50 asks users to visually inspect equipment, including before it is put into storage, and for damaged equipment or leads to be taken out of service. Damage to hotel facilities is recorded together with the organizer.

    Worked example

    The numbers in the examples below are practice numbers unless their origin is stated.

    Example 1: exhibition power demand. The stand list contains 24 small stands of 1.5 kW, 12 food stands of 4 kW, and 4 large stands of 6 kW, plus 8 kW of lighting. The total installed power is 24×1.5+12×4+4×6+8=11624 \times 1.5 + 12 \times 4 + 4 \times 6 + 8 = 116 kW. With a demand factor of 0.7 from the installer, Pd=0.7×116=81.2P_\text{d} = 0.7 \times 116 = 81.2 kW, and with a power factor of 0.8, S=81.2/0.8=101.5S = 81.2/0.8 = 101.5 kVA. The rented 100 kVA generator is not enough even before compressor starting current is considered, so the generator provider is asked to recalculate its size.

    Example 2: phase currents and neutral current. At 400 V three-phase, the current for 101.5 kVA is I=101,500/(3×400)=146.5I = 101{,}500/(\sqrt{3} \times 400) = 146.5 A per phase if perfectly balanced. After the stands are divided, the currents measured at the board are 120 A, 100 A, and 90 A. Assuming loads with a power factor close to 1, IN=1202+1002+902−120×100−100×90−90×120=700=26.5I_\text{N} = \sqrt{120^2 + 100^2 + 90^2 - 120 \times 100 - 100 \times 90 - 90 \times 120} = \sqrt{700} = 26.5 A. If two food stands are moved so that the currents become 110 A, 105 A, and 95 A, IN=1102+1052+952−110×105−105×95−95×110=175=13.2I_\text{N} = \sqrt{110^2 + 105^2 + 95^2 - 110 \times 105 - 105 \times 95 - 95 \times 110} = \sqrt{175} = 13.2 A.

    Example 3: generator location. The generator is placed 4 m from the kitchen loading door. The CDC distance is more than 20 feet, that is, 20×0.3048=6.120 \times 0.3048 = 6.1 m, so the generator is 6.1−4=2.16.1 - 4 = 2.1 m short. A new location is chosen with the generator provider away from all doors, windows, and vents, including the downwind kitchen air intake, and segregated from visitor areas.

    Example 4: voltage drop to the farthest stand. A stand at the far end of the parking area is supplied by a 60 m cable carrying 16 A. With 4 mm² conductors, ΔU=2×0.0178×60×16/4=8.54\Delta U = 2 \times 0.0178 \times 60 \times 16/4 = 8.54 V, that is, 8.54/230=3.78.54/230 = 3.7 percent. With 2.5 mm² conductors, ΔU=2×0.0178×60×16/2.5=13.7\Delta U = 2 \times 0.0178 \times 60 \times 16/2.5 = 13.7 V, that is, 5.9 percent. The installer chooses a larger cross-section or a second board that is closer.

    Example 5: number of RCDs. Forty stands each receive one final circuit. If one 30 mA RCD protects no more than six final circuits, the minimum number of RCDs is 40/6=6.740/6 = 6.7, rounded up to 7. A 300 mA RCD is installed at the generator output, which is 300/30=10300/30 = 10 times the rated current of the stand RCDs, and its time setting is chosen by the installer so that a fault at one stand trips only that stand’s RCD, not the whole exhibition.

    Example 6: cables crossing walkways. A 3 m wide guest walkway is crossed by a cable, and each cable protector ramp is 0.9 m long, so 3/0.9=3.33/0.9 = 3.3 ramps are needed, rounded up to 4 ramps. Another cable has to cross a supply truck route used by trucks up to 4.2 m tall. A 5.8 m cable bridge leaves 5.8−4.2=1.65.8 - 4.2 = 1.6 m of clearance above the tallest truck, and warning notices are placed in both directions.

    Stop conditions

    1. There is a plan or request to connect a temporary distribution board, a generator, or an exhibitor’s cable to a fixed board or hotel receptacle other than the connection points provided, or to connect a generator to the building installation without a transfer switch: do not connect and do not help to connect; hand the matter over to the hotel’s Ahli K3 bidang Listrik and the authorized installer according to Chapter 36.
    2. A temporary distribution board is open, unlocked, missing its cover, exposing live parts, or within reach of visitors: do not touch the board; keep people away with barriers from a safe distance, and call the installer to close and secure it.
    3. Cables, connections, boards, or stand equipment are submerged or standing in water, or cable insulation is damaged to the point that the cores show: do not touch and do not unplug; keep people away from the area, and ask the installer to disconnect the circuit at the source.
    4. An RCD trips repeatedly, someone feels tingling or a shock, or there is a request to move a stand to a receptacle without an RCD: stop using that stand’s equipment, do not reset the RCD again and again and do not bypass it, and hand the fault-finding over to the installer.
    5. A generator is inside a building or enclosed space, less than 6.1 m from doors, windows, or vents, or exhaust gas can be smelled indoors, or someone has symptoms of carbon monoxide poisoning: take people out to fresh air, call emergency services for anyone with symptoms, and ask the generator provider to shut down and relocate the generator.
    6. Unprotected cables cross a vehicle route, evacuation route, fire door, or ambulance route: the route is not opened to visitors until the installer moves the cable or fits suitable protectors and cable bridges.
    7. Lightning, heavy wind-driven rain, or water starting to flow toward outdoor boards and connections: stop outdoor stand activities according to the event weather plan, keep people away from electrical equipment, and ask the installer to disconnect threatened circuits.
    8. Dismantling has started before the installer has declared the source and boards dead: stop the dismantling; all cables and boards are treated as live until that declaration is given.

    Common misinterpretations

    Guess what’s wrong first, then open the explanation.

    Common misconception

    A receptacle that never trips is better than one that trips often.

    Why is it wrong?

    An RCD that trips shows that there is leakage current. Moving equipment to a receptacle without an RCD hides the fault and removes the protection against shock.

    Common misconception

    A generator outdoors is always safe from carbon monoxide.

    Why is it wrong?

    Exhaust gas can enter through nearby doors, windows, and vents. The CDC asks for generators to be more than 20 feet from those openings.

    Common misconception

    A generator does not need grounding because it is separate from the network.

    Why is it wrong?

    Without a grounded output point, a fault can make an equipment casing live without operating the protection. The generator is given its own grounding, tested by the installer.

    Common misconception

    Cables are safe as long as they are covered with carpet.

    Why is it wrong?

    Carpet hides cables but does not protect them from pressure and does not stop people tripping on the bulge. Cables on walkways use protective ramps or another route.

    Common misconception

    Once the event is over, the cables can be coiled straight away.

    Why is it wrong?

    Cables and boards remain live until the installer switches off the source and declares it dead.

    Chapter 36 on generator sets and transfer switches covers the electrical side of generators and backfeed; this chapter places portable generators at events. Chapter 18 on RCD testing, Chapter 37 on wet locations, and Chapter 114 on portable electrical equipment complete the protection discussed here, and event audiovisual equipment is in Chapter 116.

    Exercises and worked solutions

    The numbers in the exercises are for practice.

    Try to answer first, then open the worked solution.

    1. An exhibition has 30 stands with an installed power of 2 kW each and 6 kW of lighting. With a demand factor of 0.75 and a power factor of 0.8, how many kVA must the source provide?

      Check my answer
      See the worked solution

      The installed power is 30×2+6=6630 \times 2 + 6 = 66 kW, the demand power is 0.75×66=49.50.75 \times 66 = 49.5 kW, and the apparent power is 49.5/0.8=61.949.5/0.8 = 61.9 kVA. The generator size is also checked against the starting current of motor loads as in Chapter 36, because the average apparent power does not yet show the surge when a compressor starts.

    2. The three-phase currents at a temporary board are 80 A, 60 A, and 40 A with loads of power factor close to 1. What is the neutral current, and what does it mean?

      Check my answer
      See the worked solution

      The neutral current is 802+602+402−80×60−60×40−40×80=1,200=34.6\sqrt{80^2 + 60^2 + 40^2 - 80 \times 60 - 60 \times 40 - 40 \times 80} = \sqrt{1{,}200} = 34.6 A. The neutral carries a fairly large current because the phase sharing is lopsided, so the installer is asked to move some stands from the first phase to the third.

    3. The generator provider wants to place the generator 3 m from the kitchen’s fresh-air intake because it is “outdoors”. What is the technician’s answer?

      Check my answer
      See the worked solution

      The technician refuses, because the CDC asks for generators to be more than 20 feet, that is, 6.1 m, from doors, windows, and vents so that carbon monoxide does not enter. The kitchen air intake would carry exhaust gas into the workroom, so another location is chosen with the generator provider.

    4. A coffee stand’s RCD trips every time its coffee machine switches on, and the stand owner asks for a connection to a wall receptacle without an RCD. What does the technician do?

      Check my answer
      See the worked solution

      The technician refuses that connection, because an RCD that trips indicates leakage current from the appliance, and a receptacle without an RCD only removes the protection. The coffee machine is taken out of use until it is checked, and the installer looks for the fault.

    5. After rain, a distribution cable connection lies in a puddle near the guest walkway and the stand lights are still on. What is the action?

      Check my answer
      See the worked solution

      The connection is not touched and not unplugged, and people are kept away from the puddle with barriers. The technician asks the installer to disconnect the circuit at the source, because water can make the puddle live and a submerged connection is not safe to unplug by hand.

    6. A temporary board has 15 final circuits for stand receptacles. What is the minimum number of 30 mA RCDs under the six-circuits-per-RCD recommendation?

      Check my answer
      See the worked solution

      The number is 15/6=2.515/6 = 2.5, rounded up to 3 RCDs. Dividing the circuits among several RCDs also means a fault in one group of stands does not shut down the whole exhibition.

    References

    External sources

    • Electrical safety at places of entertainment (Guidance Note GS50, fourth edition)hse.gov.uk
    • Electrical safetyhse.gov.uk
    • Peraturan Menteri Ketenagakerjaan Nomor 12 Tahun 2015 tentang Keselamatan Dan Kesehatan Kerja Listrik Di Tempat Kerjajdih.kemnaker.go.id
    • Carbon Monoxide (CO) Poisoning Basicscdc.gov
    • Preventing slips and trips at work: A brief guide (INDG225)hse.gov.uk
    • Electrical safety for entertainers (INDG247(rev2))hse.gov.uk

    Revision history

    DateVersionChange
    November 15, 20261First published

    How to cite

    Kurnia (2026). Temporary power for events and exhibitions: portable generators, temporary distribution boards, cables on floors and walkways, RCDs and grounding, weather and water, and dismantling. ARSTEMA Academy. Revised November 15, 2026. arstema.com/en/academy/konsep/listrik-sementara-untuk-acara-dan-pameran-genset-portabel-panel-distribusi-sementara-kabel-di-lantai-dan-jalur-orang-rcd-dan-pembumian-cuaca-dan-air-serta-pembongkaran

    Self-check · 3 questions

    Check your understanding before moving on

    Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.

    0/3rated

    Safety limits still apply. This quiz tests reasoning; it doesn’t authorize mixing, adjusting, dismantling, live measurement, or field action.

    1

    An exhibition has 30 stands with an installed power of 2 kW each and 6 kW of lighting. With a demand factor of 0.75 and a power factor of 0.8, how many kVA must the source provide?

    2

    The three-phase currents at a temporary board are 80 A, 60 A, and 40 A with loads of power factor close to 1. What is the neutral current, and what does it mean?

    3

    The generator provider wants to place the generator 3 m from the kitchen’s fresh-air intake because it is “outdoors”. What is the technician’s answer?