Skip to content

Search ARSTEMA

Type a chapter, term, symptom, or tool.

    Safety · Chapter 16Applied

    By Kurnia · Published November 15, 2026 · Version 1 · 21 min read

    Earthquakes and hotel buildings from the engineering team’s side

    equipment readiness and restraints, first response, shutting off gas and water, rapid inspection after an earthquake, elevators and generator sets, and limits of authority

    A strong earthquake shakes a nine-story hotel at night: ceiling panels in the ballroom fall, a sprinkler pipe on the seventh floor breaks and water runs into the stairway for almost half an hour because nobody knows where its zone valve is, gas is smelled in the kitchen, and the elevators stop. This chapter covers earthquakes from the building engineering team’s side: nonstructural components and the forces acting on them, equipment readiness and restraints, first response during and after the shaking, shutting off gas and water, rapid inspection after an earthquake and its limits, elevators and generator sets, and emergency procedures under PP 50/2012. The design force equation for nonstructural components and the elevator seismic switch rule are presented as United States data. The chapter makes clear that declaring a building safe to occupy belongs to structural engineers and the competent authorities; technicians do not assess structural soundness, do not reopen the gas supply, and do not return elevators to service.

    High-risk material

    This material involves real hazards. A concept explanation doesn’t replace site procedures, competency, energy isolation, the latest SDS, or a work permit.

    Section you’re reading: Chapter opening

    At 21:40, a strong earthquake shakes a nine-story hotel for about twenty seconds. In the ballroom, several ceiling panels and a pendant light fall onto the dance floor, which happens to be empty. On the seventh floor, a branch of the sprinkler pipe breaks at a joint, and water runs into the corridor and then into the emergency stairway for almost half an hour, because the duty technician does not know which zone valve serves that branch. Kitchen staff smell gas near the row of ranges, both guest elevators stop, and the water heater on the roof shifts off its base until its pipes are bent. An hour later, the duty manager asks the chief engineer whether guests may return to their rooms. That question is not within the engineering team’s authority. The engineering team’s job is to prepare the building before an earthquake, secure the utilities after the shaking, record the damage, and hand the question of fitness for occupancy to those with the authority to answer it.

    Scope

    This chapter covers earthquakes from the hotel engineering team’s side: nonstructural components and the forces acting on them, equipment readiness and restraints, first response during and after the shaking, shutting off gas, water, and electricity, rapid inspection after an earthquake and its limits, elevators and generator sets after an earthquake, and emergency procedures within the occupational safety and health (K3) management system.

    Elevator and escalator emergency response, including during an earthquake, is in Chapter 25 · Buildings & Facilities. The generator set fuel system is in Chapter 23 · Fluids & Thermal, and total power outages with priority loads in Chapter 118 · Electrical & Control. Building natural gas piping is in Chapter 22 · Fluids & Thermal, and LPG in kitchens and storerooms in Chapter 5 · Commercial Kitchens. Cracks in walls and concrete are in Chapter 36 · Buildings & Facilities, evacuation drills in Chapter 14, fire protection and sprinklers in Chapter 17 · Buildings & Facilities, glass and windows in Chapter 50 · Buildings & Facilities, and incident investigation in Chapter 12.

    Outside the building technician’s authority: assessing structural soundness after an earthquake, declaring a building, floor, or room safe to occupy, entering heavily damaged parts of the building, designing anchors and equipment restraints, reopening a gas supply that has been shut off, returning elevators to service, and repairing damaged electrical panels. Structural assessment and declaring a building safe to occupy belong to structural engineers and the competent authorities; gas belongs to the gas utility or LPG supplier, elevators to the elevator contractor, and damaged electrical installations to an authorized electrician or licensed installer. This chapter is learning material, not an emergency response procedure; what applies is the building’s own written procedure.

    Earthquakes, building motion, and nonstructural components

    During an earthquake, the ground moves and the building sways with it. Every object attached to the building is forced to move too, and by Newton’s second law the force required is proportional to its mass: F=m aF = m\,a. If the restraint cannot supply that force, the object slides, tips over, or falls.

    Nonstructural components are the parts of a building that do not carry the building’s loads: architectural components such as ceilings, partition walls, and glass; mechanical, electrical, and plumbing systems; and building contents such as cabinets, shelving, and equipment. The range is wide, from cabinets to emergency generators and water heaters. Almost everything the engineering team maintains falls into this group, while the structure, that is, columns, beams, slabs, shear walls, and foundations, is the structural engineer’s concern.

    Most earthquake-related injuries and deaths are caused by falling or flying objects, such as televisions, lamps, glass, and bookcases, or by people being knocked to the ground. Nonstructural damage can also make a building unusable even when its structure is intact: a multistory building without a functioning elevator may not be occupiable, and loss of utilities can lead the competent authority to declare a building unoccupiable.

    The acceleration that equipment experiences depends on where it is. In the United States, the ASCE/SEI 7-16 load standard gives the horizontal design force for nonstructural components by the following equation:

    Fp=0.4 ap SDS WpRp/Ip(1+2 zh)F_p = \frac{0.4\, a_p\, S_{DS}\, W_p}{R_p / I_p}\left(1 + 2\,\frac{z}{h}\right)

    where FpF_p is the horizontal design force (N), WpW_p the operating weight of the component (N), SDSS_{DS} the design spectral response acceleration at short periods at the site (dimensionless, as a fraction of gravitational acceleration), apa_p the component amplification factor, RpR_p the component response modification factor, IpI_p the component importance factor, zz the height of the component’s attachment point above the base of the building (m), and hh the average roof height above the base (m). The equation takes the floor acceleration as the ground acceleration, approximated as 0.4 SDS0.4\,S_{DS}, increasing linearly to three times the ground acceleration at the roof. The result has a lower bound of 0.3 SDS Ip Wp0.3\,S_{DS}\,I_p\,W_p and an upper bound of 1.6 SDS Ip Wp1.6\,S_{DS}\,I_p\,W_p, and the horizontal force is combined with a vertical force of ±0.2 SDS Wp\pm 0.2\,S_{DS}\,W_p.

    This equation is presented as United States data for understanding the pattern, not for design. The value of SDSS_{DS} in Indonesia, the component factors, and the anchors are set by a structural engineer or mechanical designer under the Indonesian seismic standard in force. The lesson for technicians: equipment on the roof receives a design force up to three times that of the same equipment at the base of the building, and equipment that is not restrained is held only by friction.

    Equipment readiness and restraints

    Seismic restraint is an anchor, brace, strap, or frame that holds equipment in place during an earthquake. The same United States standard defines component supports as members, frames, legs, lugs, snubbers, hangers, saddles, or struts and their fasteners that transmit loads from the component to the structure. Equipment on spring vibration isolators, such as pumps, fans, and generator sets, is among the vulnerable items, because spring mounts are made precisely so the equipment can move freely.

    The engineering team keeps a list of equipment that could injure people or interrupt service if it shifted or fell: water heaters and tanks, rooftop air conditioning units, electrical panels and UPS battery racks, generator sets and their day tanks, storeroom, kitchen, and bar shelving, suspended ceilings and light fixtures, and gas, water, and sprinkler piping. For each item the team records its location, whether a restraint is present, and who designed it.

    The CDC preparedness guidance for homes gives rules that also apply in staff rooms, storerooms, and guest rooms: secure bookcases and shelves, anchor items into the wall studs, place heavy or large objects on lower shelves, secure the water heater with a wide metal strap around the top attached to wall studs, and know how to turn off gas, electricity, and water. For building equipment, the restraint design is made by the designer; the technician checks that the designed restraint is actually installed and intact.

    The NIST report on nonstructural components asks maintenance personnel to be aware of the importance of seismic anchorage and bracing, and that after any work on nonstructural components the lateral restraints be fully restored. The report also suggests locating critical equipment at or below grade, where accelerations are expected to be lower. A restraint removed during a unit replacement and never reinstalled is a finding worth looking for, so checking restraints belongs on the handover list for every maintenance job.

    First response during and after the shaking

    When shaking is felt, the CDC recommends three actions: drop down onto hands and knees, cover the head and neck under a sturdy table, and hold on until the shaking stops. People inside a building stay inside, do not run outside, move away from glass, hanging objects, and shelves, do not stand in a doorway, and do not use elevators. People in the kitchen turn off the stove if they can and then take cover. The most dangerous area outside is near the outer walls and doorways, because windows, facades, and architectural details are often the first parts to collapse.

    After the shaking stops, aftershocks can occur minutes, days, weeks, or even months later, and each time one is felt, people again drop, cover, and hold on. People do not enter a damaged building until local authorities say it is safe, and they leave a building if they hear unusual shifting noises.

    For hotels on the coast, the CDC writes that if severe shaking lasts 20 seconds or more, people should immediately evacuate to high ground, about 3 km inland or to a place at least 30 m above sea level, without waiting for an official warning. That is United States guidance; in Indonesia, a coastal hotel’s emergency response plan adapts it to BMKG tsunami early warnings and the evacuation routes set by the local government.

    The engineering team’s role begins after the shaking stops and its own members are safe. The duty technician reports to the emergency response coordinator and reads the fire alarm panel without resetting anything, then one group goes to the utilities and another sweeps the floors with the evacuation wardens. A fire after an earthquake is handled under Chapter 14 on evacuation drills and Chapter 17 · Buildings & Facilities on fire protection.

    Shutting off gas, water, and electricity

    Gas. The CDC writes that if gas is smelled or a broken line is seen, the main valve is shut off from the outside, and once the gas is turned off, a professional must restore service. Matches, lighters, appliances, and light switches are not used until it is certain there are no gas leaks, because sparks from switches can ignite gas and cause an explosion. Natural gas emergency valves are covered in Chapter 22 · Fluids & Thermal and LPG in Chapter 5 · Commercial Kitchens. The valve is closed by the person designated in the procedure, and the supply is reopened only by the gas utility or LPG supplier, after all lines and appliances have been checked.

    Water. The NIST report notes that water released from suspended pressurized piping, such as sprinkler piping, can ruin materials, grow mold, and flow into several floors below, and that the duration of the leak strongly determines the extent of the damage. The report suggests placing shut-off valves strategically, giving clear wayfinding to them, and training maintenance personnel in valve locations and procedures. The volume of water released is calculated simply:

    V=Q×tV = Q \times t

    where VV is the volume of water (L), QQ the flow rate from the broken pipe (L/s), and tt the time the water flows until the valve is closed (s). The assumption is a constant flow rate; the actual rate depends on the pressure and the size of the break.

    Closing a sprinkler zone valve leaves that zone without fire protection, even though a fire after an earthquake is possible. The zone valve is closed under the procedure in Chapter 17 · Buildings & Facilities, with the emergency response coordinator’s knowledge, the time and zone are recorded, and the repair is handed to the fire protection contractor.

    Electricity. If a panel has shifted, there is a burning smell, or water has pooled near electrical equipment, the designated electrical staff cut the supply from an upstream panel located in a dry, safe place. Technicians do not walk into the pooled water and do not re-energize damaged circuits. Fallen power lines are kept clear of and reported to the electric company.

    Rapid inspection after an earthquake and its limits

    Rapid post-earthquake inspection is a sweep of the building by the engineering team to find hazards that must be controlled right away: gas, water, and fuel leaks, electrical damage, shifted equipment, ceilings and light fixtures about to fall, broken glass, blocked exit routes, and failed emergency lights. This inspection does not assess the structure; its purpose is to control hazards, record, and report.

    The CDC recommends checking walls, floors, doors, windows, and staircases; if structural damage is seen, such as cracks in the foundation or missing support beams, people may need to relocate to another safe place. For technicians, such signs, as well as wide cracks or tilting in columns and beams, spalled concrete exposing reinforcement, sagging floors, or a door that suddenly jams in its frame, are reasons to stop: people are moved out of the area, the area is cordoned off, photographed from a safe place, and reported. Crack width measurement in Chapter 36 · Buildings & Facilities is used for ordinary cracks monitored over time, not for deciding whether a building is fit for occupancy after an earthquake.

    In the United States, after a disaster, local building departments organize teams of inspectors who assess damaged buildings and post colored tags: green means no hazards, yellow means the building is moderately damaged and its use is limited, and red means the building is unsafe and must not be entered under any circumstances. In Indonesia, the declaration that a building is safe to reoccupy is made by structural engineers and the competent authorities. The hotel engineering team provides building drawings, access, and the rapid inspection records, which state the time, location, findings, actions already taken, and who was informed; those records are used again for the investigation (Chapter 12).

    Elevators and generator sets after an earthquake

    Elevators. The CDC advises against using elevators during an earthquake because the power may go out and the sprinklers may come on. In the United States, elevators are designed to the seismic requirements of the ASME A17.1 elevator safety code as modified by ASCE/SEI 7-16; elevators operating at a speed of 150 ft/min (46 m/min) or more must be provided with a seismic switch, a sensor that stops the elevator when shaking is detected, and the cars and counterweights must have retainer plates at the top and bottom. That is a United States rule; the seismic equipment of elevators in Indonesian buildings is a question for the elevator contractor. Under Chapter 25 · Buildings & Facilities, the decision to use elevators again after an earthquake is made by the building management together with the elevator contractor, and trapped passengers are rescued by trained persons.

    Generator sets. When the utility supply fails, the generator set starts and carries the priority loads (Chapter 118 · Electrical & Control). After an earthquake, the technician checks from outside the generator room: the smell and pooling of diesel fuel, fuel lines and exhaust pipes that are broken or detached, a generator set that has shifted off its spring mounts, and a tilted day tank. If any of these is found, the generator set is shut down under the procedure and handed to the generator technician (Chapter 23 · Fluids & Thermal). If the transfer line from the main storage tank is damaged, only the day tank is available, so the run time is recalculated. Portable generator sets are not run inside the building, a basement, or a garage, and are placed outside, at least 20 feet from any window, door, or vent, because carbon monoxide has no smell and cannot be seen.

    Emergency procedures and limits of authority

    In Indonesia, PP 50/2012 (Government Regulation) on the implementation of the occupational safety and health management system (SMK3) requires companies to have procedures for dealing with accident emergencies and industrial disasters. Those procedures must be tested periodically by personnel with work competence, and the company must have a procedure for rapid emergency recovery planning to return to normal conditions. The audit criteria in its annex require that potential emergencies be identified, procedures documented and communicated, emergency response officers appointed and trained, and emergency equipment and alarm systems inspected, tested, and maintained periodically. As of November 2026, JDIH Kemnaker lists PP 50/2012 as in force. For hotels in Indonesia, an earthquake is a potential emergency, so an earthquake procedure is among those that must exist and be tested. The division of work:

    TaskHotel engineering teamWho takes over
    Equipment restraintslist, inspect, reinstall after maintenancethe mechanical designer or structural engineer designs them
    Gas after an earthquakeclose the emergency valve if designated, keep people awaythe gas utility or LPG supplier reopens the supply
    Water and sprinklersclose the leaking zone valve under the procedurethe plumbing contractor and fire protection contractor
    Electricitycut the supply from a safe upstream panel if designatedan authorized electrician or licensed installer
    Elevatorskeep guests away, reassure trapped passengersthe elevator contractor
    Building structurerecord, photograph, cordon off the areastructural engineers and the competent authorities

    Worked example

    The figures in the examples below are practice figures, unless their origin is stated.

    Example 1: design force on a water heater at the base of the building and on the roof. A water heater with a mass of 400 kg weighs Wp=400×9.81=3,924W_p = 400 \times 9.81 = 3{,}924 N. With SDS=0.8S_{DS} = 0.8, ap=1.0a_p = 1.0, Rp=2.5R_p = 2.5, and Ip=1.0I_p = 1.0, at the base of the building (z=0z = 0) the main equation gives Fp=0.4×1.0×0.8×3,924/2.5=502.3F_p = 0.4 \times 1.0 \times 0.8 \times 3{,}924 / 2.5 = 502.3 N. The lower bound 0.3×0.8×1.0×3,924=941.80.3 \times 0.8 \times 1.0 \times 3{,}924 = 941.8 N is larger, so the design force is 941.8 N. On the roof (z=hz = h), the height factor 1+2×1=31 + 2 \times 1 = 3 gives 502.3×3=1,506.9502.3 \times 3 = 1{,}506.9 N, still below the upper bound 1.6×0.8×1.0×3,924=5,022.71.6 \times 0.8 \times 1.0 \times 3{,}924 = 5{,}022.7 N. On the roof, the design force is 1,506.9/941.8=1.61{,}506.9/941.8 = 1.6 times the force at the base; the actual values are set by the designer.

    Example 2: a storeroom rack that tips over. A kitchen storeroom rack 2.0 m tall and 0.45 m deep is evenly loaded, so its center of mass is at mid-height, hc=1.0h_c = 1.0 m. An unanchored rack tips over if the moment of the horizontal force about its bottom edge exceeds the moment of its weight:

    ag>b2 hc\frac{a}{g} > \frac{b}{2\,h_c}

    where aa is the horizontal acceleration (m/s²), gg the gravitational acceleration (m/s²), bb the depth of the rack (m), and hch_c the height of the center of mass (m), assuming the rack is rigid and does not slide. The threshold is 0.45/(2×1.0)=0.2250.45/(2 \times 1.0) = 0.225. If heavy items are moved to the lower shelves so that hc=0.7h_c = 0.7 m, the threshold rises to 0.45/(2×0.7)=0.3210.45/(2 \times 0.7) = 0.321. The design force in Example 1 is equivalent to 941.8/3,924=0.24941.8/3{,}924 = 0.24 times the weight at the base and 1,506.9/3,924=0.3841{,}506.9/3{,}924 = 0.384 times the weight on the roof, so a rack that tall is still anchored.

    Example 3: water from a broken sprinkler pipe. The broken branch pipe discharges 2.5 L/s. If the zone valve is closed only after 30 minutes, that is, 1,800 s, the water released is V=2.5×1,800=4,500V = 2.5 \times 1{,}800 = 4{,}500 L. If the valve is closed within 6 minutes, that is, 360 s, the water is 2.5×360=9002.5 \times 360 = 900 L, which is 4,500−900=3,6004{,}500 - 900 = 3{,}600 L or 80 percent less, because the valve location is known and signposted.

    Example 4: elevator speed and the United States seismic switch threshold. The threshold of 150 ft/min equals 150×0.3048=45.72150 \times 0.3048 = 45.72 m/min, written as 46 m/min. A guest elevator rated at 1.6 m/s travels 1.6×60=961.6 \times 60 = 96 m/min, above that threshold, so under the United States rule it must have a seismic switch. A service elevator at 0.6 m/s travels 0.6×60=360.6 \times 60 = 36 m/min, below the threshold. In Indonesia, this result becomes a question for the elevator contractor.

    Example 5: generator set run time when the transfer line is damaged. The generator set’s day tank holds 400 L. At full load the generator set uses 50 L/h, so the day tank runs out in 400/50=8400/50 = 8 hours. If the load is reduced to priority loads with a consumption of 32 L/h, the run time is 400/32=12.5400/32 = 12.5 hours. An additional portable generator set is placed at least 20 feet, that is, 20×0.3048=6.120 \times 0.3048 = 6.1 m, from windows, doors, and vents.

    Example 6: planning the rapid inspection. A 12-story hotel with a basement and a roof has three teams. Team A goes to the gas room, the pump room and main water valves, the main panel, and the generator room, 10 minutes each: 4×10=404 \times 10 = 40 minutes. Team B sweeps floors 1 to 6 and the basement: 6×4+10=346 \times 4 + 10 = 34 minutes. Team C sweeps floors 7 to 12 and the roof: 6×4+12=366 \times 4 + 12 = 36 minutes. The inspection is complete in about 40 minutes, and the utilities come first because gas and water leaks get worse every minute.

    Stop conditions

    1. Gas is smelled or hissing is heard after the earthquake: do not turn switches, lighters, or electrical appliances on or off, keep people away, and close the emergency valve from outside the area only if you are the designated person and the route is safe; call the gas utility or LPG supplier and the fire department; the gas supply is reopened only by the gas utility or LPG supplier.
    2. Wide cracks, tilting, or spalled concrete are seen in columns and beams, floors are sagging, or shifting noises are heard: move people out of that area, put up a cordon, do not go back in, and hand the assessment to structural engineers and the competent authorities.
    3. Management asks a technician to declare a building, floor, or room safe to occupy: do not make that declaration; hand the decision to structural engineers and the competent authorities.
    4. An aftershock is felt during the inspection: stop the inspection, drop, cover, and hold on, then leave the damaged area after the shaking stops; the emergency response coordinator decides whether the inspection continues.
    5. Water has pooled near a panel or electrical equipment, or a power line has fallen: do not walk into the pooled water and do not touch the line; the designated electrical staff cut the supply from a safe upstream panel, lines outside the building are reported to the electric company, and repairs are handed to an authorized electrician or licensed installer.
    6. An elevator has stopped, passengers are trapped, or the elevator has not been inspected since the earthquake: do not open the elevator doors and do not run the elevator; call the elevator contractor under Chapter 25 · Buildings & Facilities, and the elevator is not used until the building management and the elevator contractor decide so.
    7. A generator set has shifted off its mounts, a diesel leak is smelled or seen, or an exhaust pipe has come loose: shut down the generator set under the procedure from outside the room if it is safe, do not restart it, and hand it to the generator technician; diesel spills are handled under Chapter 23 · Fluids & Thermal.
    8. A sprinkler pipe is broken and has to be shut off: close the zone valve under the procedure in Chapter 17 · Buildings & Facilities with the emergency response coordinator’s knowledge, record the time and the zone left without protection, and hand the repair to the fire protection contractor.
    9. At a coastal hotel, strong shaking lasts a long time or there is an official tsunami warning: stop all inspections, join the evacuation to high ground under the emergency response plan, and do not return until the competent authorities declare it safe.

    Common misinterpretations

    Guess what’s wrong first, then open the explanation.

    Common misconception

    During an earthquake, the safest thing is to run out of the building.

    Why is it wrong?

    People inside are less likely to be injured if they stay where they are and take cover, while the area near outer walls and doorways is where objects from the facade most often fall.

    Common misconception

    A doorway is the best place to shelter.

    Why is it wrong?

    In modern buildings, a doorway is no stronger than any other part and does not protect against falling or flying objects, the most common cause of injury. A sturdy table is better.

    Common misconception

    If the walls are not cracked, the building is surely safe to reoccupy.

    Why is it wrong?

    Structural damage is not always visible from a tidy room, and nonstructural damage such as loss of utilities or elevators can also make a building unoccupiable. The decision to reoccupy belongs to structural engineers and the competent authorities.

    Common misconception

    Once the gas smell is gone, the valve may be opened again.

    Why is it wrong?

    Gas shut off after an earthquake is reopened by a professional after the lines and appliances have been checked, because a cracked pipe behind a wall cannot be seen from outside.

    Common misconception

    Equipment restraints only need to be installed once, during construction.

    Why is it wrong?

    Restraints can be removed during maintenance or unit replacement and never reinstalled. Lateral restraints are fully restored after every job, and checking restraints belongs on the handover list.

    Chapter 25 · Buildings & Facilities on elevator emergency response, Chapter 118 · Electrical & Control on total power outages, and Chapter 23 · Fluids & Thermal on generator set fuel continue the section on elevators and generator sets. Shutting off gas draws on Chapter 22 · Fluids & Thermal on natural gas piping and Chapter 5 · Commercial Kitchens on LPG, sprinklers on Chapter 17 · Buildings & Facilities on fire protection, and cracks monitored under normal conditions are in Chapter 36 · Buildings & Facilities.

    Exercises and worked solutions

    The figures in the exercises are for practice.

    Try to answer first, then open the worked solution.

    1. The water heater in Example 1 is moved to a middle floor (z/h=0.5z/h = 0.5). What is its design force with the same factors?

      Check my answer
      See the worked solution

      The height factor becomes 1+2×0.5=21 + 2 \times 0.5 = 2, so the main equation gives 502.3×2=1,004.6502.3 \times 2 = 1{,}004.6 N. That value is above the lower bound of 941.8 N and below the upper bound of 5,022.7 N, so the design force is 1,004.6 N, between the values at the base and on the roof.

    2. A filing cabinet 1.8 m tall and 0.3 m deep is evenly loaded. At what acceleration ratio does an unanchored cabinet start to tip over?

      Check my answer
      See the worked solution

      The threshold is b/(2hc)=0.3/(2×0.9)=0.167b/(2h_c) = 0.3/(2 \times 0.9) = 0.167, lower than for the rack in Example 2 because the cabinet is more slender. Such a cabinet tips over easily, so it is anchored to the wall and heavy items are kept in the bottom drawers.

    3. After the earthquake, kitchen staff smell gas and want to switch on a light so they can see the source. What should be done?

      Check my answer
      See the worked solution

      Lights and switches are not touched, because a spark from a switch can ignite the gas. Staff keep people away and report; the emergency valve is closed from outside the area by the designated person, and the gas utility or LPG supplier is called to inspect and reopen the supply.

    4. The duty manager asks the chief engineer to announce that floors 3 to 5 are safe because no cracks are visible. How should the chief engineer respond?

      Check my answer
      See the worked solution

      The chief engineer does not make that announcement, because structural soundness cannot be judged from the absence of visible cracks and is not within the engineering team’s authority. The rapid inspection records and building drawings are handed to structural engineers and the competent authorities, who decide.

    5. A broken cold water pipe discharges 1.5 L/s and is shut off only 40 minutes later. How much water is released, and what is the lesson?

      Check my answer
      See the worked solution

      The volume is 1.5×40×60=3,6001.5 \times 40 \times 60 = 3{,}600 L, enough to flood several floors below. The lesson is the same as in Example 3: shut-off valve locations are signposted and technicians are trained, because the duration of the flow determines the extent of the damage.

    6. Two hours after the earthquake, the elevator contractor has not arrived and an elderly guest asks for the elevator to be run. What does the technician do?

      Check my answer
      See the worked solution

      The elevator is not run, because the decision to use elevators again after an earthquake is made by the building management together with the elevator contractor, and the elevator may be damaged without visible signs. The guest is helped under their personal emergency evacuation plan, for example by being accommodated on the ground floor, while the contractor continues to be contacted.

    References

    External sources

    • Safety Guidelines: During an Earthquakecdc.gov
    • Safety Guidelines: After an Earthquakecdc.gov
    • Recommendations for Improved Seismic Performance of Nonstructural Components (NIST GCR 18-917-43)nvlpubs.nist.gov
    • A Framework to Evaluate the Cost-Effectiveness of Recovery-Based Design (NIST SP 1277)nvlpubs.nist.gov
    • Peraturan Pemerintah Republik Indonesia Nomor 50 Tahun 2012 tentang Penerapan Sistem Manajemen Keselamatan dan Kesehatan Kerjajdih.kemnaker.go.id

    Revision history

    DateVersionChange
    November 15, 20261First published

    How to cite

    Kurnia (2026). Earthquakes and hotel buildings from the engineering team’s side: equipment readiness and restraints, first response, shutting off gas and water, rapid inspection after an earthquake, elevators and generator sets, and limits of authority. ARSTEMA Academy. Revised November 15, 2026. arstema.com/en/academy/konsep/gempa-bumi-dan-gedung-hotel-dari-sisi-tim-teknik-kesiapan-peralatan-dan-pengikat-tanggap-pertama-penutupan-gas-dan-air-pemeriksaan-cepat-sesudah-gempa-lift-dan-genset-serta-batas-kewenangan

    Self-check · 3 questions

    Check your understanding before moving on

    Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.

    0/3rated

    Safety limits still apply. This quiz tests reasoning; it doesn’t authorize mixing, adjusting, dismantling, live measurement, or field action.

    1

    The water heater in Example 1 is moved to a middle floor (z/h=0.5z/h = 0.5). What is its design force with the same factors?

    2

    A filing cabinet 1.8 m tall and 0.3 m deep is evenly loaded. At what acceleration ratio does an unanchored cabinet start to tip over?

    3

    After the earthquake, kitchen staff smell gas and want to switch on a light so they can see the source. What should be done?

    Self-assessment progress0%

    Nearby chapters