By Kurnia · Published November 15, 2026 · Version 1 · 21 min read
Asbestos and hazardous materials when renovating old buildings
where asbestos is found in a building, surveys before demolition, lead paint, silica dust, separating the work area, and the limits of the work
Renovating rooms and service areas in a hotel or hospital built decades ago can break into asbestos, lead paint, and materials that release silica dust. This chapter covers all three from the building technician’s side: where asbestos is commonly found according to the British HSE guidance, why a refurbishment and demolition survey is made before work starts, how to read the threshold limit values of Permenaker 5/2018 and the British control limit together with their reference periods, the United States lead paint rule as a point of comparison, silica dust control, separating the work area, and what to do when a suspected asbestos material is found by accident. Opening, sampling, and cleaning up suspected asbestos materials, testing and stripping lead paint, and assessing exposure are stated as the work of surveyors, laboratories, industrial hygienists, and licensed or authorized contractors.
This material involves real hazards. A concept explanation doesn’t replace site procedures, competency, energy isolation, the latest SDS, or a work permit.
A hotel built in 1987 begins renovating the bathrooms on its third floor. A technician has already fitted a drill bit to run cable through the corridor ceiling when their supervisor notices that the ceiling board is different from ordinary gypsum: harder, pale gray, and crumbly at the edges. In the boiler room below, the old pipe insulation wrapping is torn and white powder has fallen near the laundry trolley route. The engineering manager stops both jobs until a survey has been done.
The HSE, the British workplace safety authority, records that asbestos insulating board was used in partitions, bulkheads above ceilings, fire door panels, elevator shaft linings, and ceiling tiles, and is difficult to tell apart from ordinary board, while asbestos pipe insulation is among the most dangerous materials because its fibers are released into the air very easily. The question “is there asbestos or not” is answered by a survey, not by a guess made at the top of a ladder.
Scope
This chapter covers asbestos, lead paint, and silica dust during the renovation of old buildings from the building technician’s side, including asbestos registers and surveys, threshold limit values, separating the work area, and the division of work. The Indonesian regulations used are Permenaker 5/2018 and Permenaker 3/1985 (Minister of Manpower Regulations); the HSE guidance and the EPA lead paint rule are written as British and United States rules, not Indonesian ones.
This chapter gives no steps for opening, sampling, wrapping, or cleaning up suspected asbestos materials, and no method for testing or stripping lead paint. That work belongs to asbestos surveyors, laboratories, industrial hygienists, and contractors licensed or authorized to handle asbestos and lead. A licensing scheme for asbestos contractors in Indonesia could not be confirmed from the documents opened as of November 2026; the building manager checks the requirements. The building technician reads the register, stops the work, closes off access, and reports.
Paints and coatings are covered in Chapter 37 · Buildings & Facilities on paints and coatings, cracks and plaster in Chapter 36 · Buildings & Facilities on cracks in walls and concrete, B3 waste in Chapter 35 · Water & Water Treatment on B3 waste, and dust and the airways in Chapter 36 · Biology & Microbiology on breathing and workplace air.
Why asbestos is dangerous and where it hides
Asbestos is a group of naturally occurring fibrous minerals that were once widely used because they are strong and heat resistant. Its fibers are fine enough to be breathed deep into the lungs. The HSE records four main diseases caused by asbestos, namely mesothelioma, asbestos-related lung cancer, asbestosis (scarring of the lungs), and diffuse pleural thickening, with symptoms that can appear 15 to 60 years after exposure. Exposure today is not felt today, and repeated exposure accumulates.
Asbestos-containing materials that are intact and undisturbed present no risk; the danger arises when the material is damaged or disturbed so that fibers are released. That is why renovation is the most dangerous time for an old building: material that has sat quietly behind a ceiling for years is drilled, cut, or broken in a single day.
The locations of asbestos-containing materials recorded by the HSE for buildings in Great Britain are summarized below.
| Material | Common locations and notes |
|---|---|
| Asbestos insulating board | partitions, bulkheads above ceilings, fire door panels, elevator shaft linings, ceiling tiles; looks like ordinary board |
| Asbestos cement products | corrugated roofing, wall cladding, gutters, flues, water and sewage pipes; hard, gray |
| Floor coverings | PVC and thermoplastic tiles, bitumen adhesive; can be hidden under carpet |
| Textured decorative coatings | patterned ceilings and walls; often painted over |
| Textiles and gaskets | rope seals, flange gaskets, old fuse boards |
| Thermal insulation | boilers, calorifiers, hot pipes; flakes easily, often covered with paint |
| Sprayed coatings | underside of roofs, steel beams and columns; up to 85 percent asbestos |
| Loose fill insulation | wall cavities, under floorboards, lofts; pure asbestos, the most dangerous |
Asbestos-containing materials are most often found in places guests rarely see but the engineering team often touches: ceiling voids, plant rooms, pipe and elevator shafts, and service floors. Asbestos also cannot be identified by its color, because the fibers may be mixed with other materials that change their appearance.
Old buildings, the asbestos register, and the management survey
The year of construction is the first clue, but what it means depends on the country. In Great Britain, asbestos-containing materials were used in new and refurbished buildings until 1999, when all use of asbestos was banned, and the HSE writes that asbestos may be part of any commercial or domestic building that was built or refurbished before the year 2000.
That cutoff year cannot be transferred to Indonesia. Permenaker 3/1985 still described asbestos as a building material that could not yet be replaced, prohibited blue asbestos (crocidolite) and the spraying of asbestos, but did not prohibit other forms. The year of a complete ban in Indonesia was not found in the documents opened, so even a younger building is not assumed to be asbestos free without evidence.
An asbestos register is a record of the location, type, and condition of materials known or presumed to contain asbestos in a building. The HSE calls the register part of the asbestos management plan and asks for it to be updated at least once a year. In a hotel, the register is opened before a work permit is signed.
A management survey is the standard survey for a building in use. Its purpose is to locate suspected asbestos materials that could be damaged during normal occupancy, including foreseeable maintenance, and to assess their condition; the areas inspected include under floor coverings, ceiling voids, lofts, risers, ducts, elevator shafts, and basements. This survey may use samples or may presume that materials contain asbestos without sampling. Areas the surveyor cannot access must be presumed to contain asbestos, stated clearly in the report, and not worked on until they have been checked further.
The refurbishment and demolition survey before work starts
A refurbishment and demolition survey is needed before any refurbishment or demolition work, to locate all asbestos-containing materials in the area to be refurbished, or in the whole building if it is to be demolished. This survey is destructive where necessary: tiles are lifted and walls and ceilings are broken through.
There are three requirements that concern hotels. A refurbishment survey is carried out only in unoccupied areas; for minor refurbishment, the survey area is effectively isolated, for example with a full floor to ceiling partition, and staff must not remain in the room while destructive sampling is in progress. The surveyed area must be shown to be fit for reoccupation before people return, through a thorough visual inspection and, where appropriate, air sampling. For buildings with many units such as hotels, the refurbishment survey only needs to cover the rooms that will be refurbished.
The British asbestos regulations also require asbestos-containing materials to be removed as far as reasonably practicable before major refurbishment, and the survey report to be supplied to the designers and contractors bidding for the work. The sequence for a hotel engineering team: the scope of the renovation is set, a survey is ordered for that scope, the results are read together with the contractor, the asbestos-containing materials are handled by an authorized contractor, and only then does the interior work begin. If the scope grows, a survey of the additional area is ordered first.
Threshold limit values and their reference periods
Permenaker 5/2018 defines the threshold limit value (Indonesian nilai ambang batas, NAB) as the standard for a workplace hazard factor in the form of a time-weighted average concentration that workers can tolerate without causing illness or health problems, for no more than 8 hours a day or 40 hours a week. The regulation also defines the permitted short-term exposure (Indonesian pajanan singkat diperkenankan, PSD), a concentration that must not be exceeded for an exposure of no more than 15 minutes and no more than 4 times a day, and the permitted ceiling concentration (Indonesian kadar tertinggi diperkenankan, KTD), which must not be exceeded even for an instant.
The time-weighted average is calculated with:
where is the concentration in interval (fibers/ml or mg/m³), is the length of that interval (hours), and is the reference period (hours). The concentration within each interval is taken as constant, and time without exposure is counted at zero concentration. A low average can hide a high peak.
The annex to Permenaker 5/2018 lists asbestos in all forms with a value of 0.1 fibers/ml and category A1, confirmed human carcinogen, and notes that blue asbestos is prohibited. In the copy that was opened, that value is printed in the PSD/KTD column, not in the NAB column, without explanation. The technician does not interpret that placement on their own; the exposure assessment is left to an industrial hygienist.
In Great Britain, the control limit for asbestos is 0.1 fibers per cubic centimeter of air averaged over a continuous period of 4 hours, and exposure classed as sporadic and of low intensity must not exceed 0.6 fibers/cm³ measured over 10 minutes. The unit fibers/cm³ is the same as fibers/ml. The value is the same as Indonesia’s, but the reference period differs (Example 1).
A threshold value does not mean that exposure below it is safe to leave alone, because asbestos is classed as a human carcinogen. Permenaker 3/1985 requires special respirators in places where the asbestos concentration exceeds the threshold limit value. For the technician, the value is used to understand an expert’s report, not to decide alone that a room may be entered.
Lead paint during renovation
Lead-based paint is paint whose pigment or drier contains lead compounds. Intact paint is relatively stable, but scraping, sanding, burning, or heating old paint produces lead dust and chips that are inhaled or swallowed. The annex to Permenaker 5/2018 sets the NAB for lead and its inorganic compounds, as Pb, at 0.05 mg/m³, category A3 (animal carcinogen), with central and peripheral nervous system disorders and hematological effects noted.
The renovation rule of the EPA, in the United States, applies to work that disturbs paint in houses, apartments, and child-occupied facilities built before 1978, including maintenance, electrical work, plumbing, and window replacement, and firms paid to do that work must be certified. Minor repairs that disturb no more than 6 square feet of paint per room inside, or 20 square feet outside, are excluded, but window replacement and demolition of painted surfaces are always covered. Without documentation that the paint is not lead-based, the requirements of the rule still apply.
The EPA gives three examples of lead-safe work practices: the work area is contained so that dust and debris do not leave it, open-flame burning and power tools without HEPA-filtered exhaust control are prohibited, and the area is cleaned thoroughly and then verified. That rule does not apply in Indonesia, and an Indonesian limit for the lead content of old paint in buildings was not found in the documents opened. This chapter uses the EPA rule as a comparison for how to think: old paint that will be disturbed is presumed to contain lead until it has been tested by an authorized tester, and the work is handed to an authorized contractor.
Silica dust from cutting and chasing
Respirable crystalline silica is dust from quartz and similar minerals that is fine enough to reach the deepest parts of the lungs. The HSE writes that this dust is created when concrete, mortar, and sandstone are worked, and that the main diseases from construction dust include lung cancer, silicosis, chronic obstructive pulmonary disease, and asthma. The annex to Permenaker 5/2018 sets the NAB for crystalline silica, quartz and cristobalite, at 0.025 mg/m³ marked R and category A2, suspected human carcinogen.
According to the HSE, high dust levels are caused by the task (cut-off saws, grinders, and abrasive blasters produce a lot of dust in a short time), an enclosed space, time, and frequency. The controls come in order. First, dust is reduced at its source by using correctly sized materials, less powerful tools, or another work method. Second, dust is stopped from getting into the air with water supplied continuously for the whole job, because wetting the material before cutting is not enough, or with on-tool extraction using an H or M class filter unit, not an ordinary commercial vacuum cleaner.
Third, respiratory protective equipment. The HSE gives an assigned protection factor of 20 as the general level for construction dust, meaning the wearer breathes only one twentieth of the dust in the air, provided the mask passes face fit testing and wearers of tight-fitting masks are clean shaven. The relationship is:
where is the concentration in the surrounding air, is the concentration breathed behind the mask, and APF is the assigned protection factor. This formula holds only when the mask fits and is worn correctly. The HSE calls respiratory protective equipment the last line of protection.
Separating the work area and unexpected finds
Work area isolation is separating the work area from the parts of the building still in use, so that dust does not spread and people with no business there do not enter. For construction dust, the HSE lists limiting the number of people near the work, enclosing the work with sheeting or temporary screens, and general mechanical ventilation in enclosed spaces. For asbestos surveys, the HSE guidance asks for a full floor to ceiling partition. In a hotel that stays open, laundry trolley routes, shared air ducts, and service elevators are dust escape routes that are often forgotten. The technician gives the locations of those ducts and routes to the contractor before work starts.
When a suspected asbestos material is found without a survey, for example during an emergency repair, the HSE guidance sheet says: stop work immediately, make sure nobody enters the area, put up a warning sign, report to the person in charge, and arrange for a sample of the material to be analyzed; work continues only if the material is shown not to contain asbestos. The same sheet also asks that no sweeping brush be used, because a brush spreads asbestos, and hands the clean-up of higher risk materials such as insulation, loose fill, and asbestos coatings to a licensed contractor. Permenaker 3/1985 prohibits cleaning asbestos dust with compressed air, and requires asbestos waste containers to be fully sealed and marked “Bahan asbes tidak boleh dihirup” (asbestos material must not be inhaled). Disposal is not the technician’s work; B3 waste is covered in Chapter 35 · Water & Water Treatment on B3 waste.
Limits of the work: who does what
In Great Britain, licensed work may be done only by holders of a license from the HSE, among other cases when exposure is not sporadic and of low intensity, when the risk assessment cannot show that the control limit will not be exceeded, or when the work involves asbestos coatings. Work on asbestos insulation or asbestos insulating board is also licensed when it is not short duration, that is, when the total time of all workers exceeds 2 hours in 7 days or one person works more than 1 hour in 7 days. Lower risk work may be done by non-licensed workers, but those workers must be trained to recognize asbestos and work safely with it. So even “small” work on asbestos requires specific training. For the building technician in this book, the line does not depend on that British division:
| Work | Done by |
|---|---|
| Keeping the register, matching the renovation scope against the survey report | building engineering team |
| Stopping work, closing off access, putting up signs, reporting | whoever finds it, then the engineering manager |
| Asbestos surveys and sampling of materials | competent asbestos surveyor |
| Analysis of material samples and air samples | authorized laboratory |
| Exposure assessment and measurement of airborne concentrations | industrial hygienist |
| Opening, removing, cleaning up asbestos materials, declaring an area fit for reoccupation | contractor licensed or authorized to handle asbestos, together with a surveyor or analyst |
| Testing and stripping lead paint | tester and contractor authorized for lead |
| Cutting and chasing with dust control | renovation contractor, with a written method of work |
Permenaker 3/1985 states that asbestos dust analysis is carried out by the Pusat Bina Hiperkes (the ministry’s occupational hygiene center) or another laboratory approved by the Minister. That regulation was written for companies that use asbestos in production, so whether it applies to building renovation is a question for an occupational safety and health (K3) expert. As of November 2026, JDIH Kemnaker (the ministry’s legal documentation network) lists Permenaker 3/1985 and Permenaker 5/2018 as in force, and Permenaker 11/2026 only revokes a few articles of Permenaker 5/2018 that do not concern the NAB annex.
Worked example
The numbers in the examples below are practice numbers unless their origin is stated, and the same applies to the year the hotel in the opening case was built.
Example 1: the reference period reverses the conclusion. A hygienist measures the fiber concentration while a contractor removes ceiling panels: 0.3 fibers/ml for 1 hour, 0.05 fibers/ml for 3 hours, and zero for the remaining 4 hours. Over an 8-hour period, fibers/ml. Over a 4-hour period containing the removal hour, fibers/ml, above the British control limit of 0.1 fibers/ml. The peak is times the value of 0.1.
Example 2: the number of fibers inhaled. A worker breathes 20 L/min, that is, 20,000 ml/min, for 60 minutes in air containing 0.1 fibers/ml. The number of fibers inhaled is the concentration times the breathing rate times the time, fibers. At 0.01 fibers/ml the number is still fibers. A threshold value is not the same as zero fibers, so the aim of control is to stop fibers from being released.
Example 3: average silica dust over a day. A contractor’s worker cuts tiles and concrete with a grinder without water for 1.5 hours at 0.4 mg/m³, then spends the remaining 6.5 hours in an area at 0.01 mg/m³. The 8-hour average is mg/m³, that is, times the NAB for crystalline silica, even though the cutting lasted less than two hours.
Example 4: a mask alone is not enough. The silica dust concentration near the grinder is 0.4 mg/m³, and the worker wears a well-fitting APF 20 mask. The concentration breathed is mg/m³, below 0.025 mg/m³ by a small margin. If the concentration rises to 0.8 mg/m³ because the room is more enclosed, the concentration behind the mask becomes mg/m³, above the NAB. Water or on-tool extraction lowers first; the mask becomes the last layer.
Example 5: paint area in the units of the United States rule. With 1 foot = 0.3048 m, the EPA exclusion of 6 square feet equals m² and 20 square feet equals m². Scraping paint from a frame and wall over m² indoors exceeds 0.557 m², so in the United States that job does not count as a minor repair. In Indonesia that figure is only a comparison; old paint that has not been tested is still treated as lead paint, whatever the area.
Example 6: the time condition for short duration work in Great Britain. Three of the contractor’s workers each work 50 minutes on asbestos insulating board in one week. The total is minutes, that is, 2.5 hours, exceeding 2 hours in 7 days, even though nobody works more than 1 hour. Two workers at 45 minutes each give minutes and meet the time condition, but the conditions of sporadic and low intensity exposure and of the control limit not being exceeded still have to be shown by a risk assessment. This decision belongs to the contractor and the risk assessor, not the technician.
Stop conditions
- A material that may contain asbestos is found or damaged during work, for example old ceiling board, pipe insulation, vinyl tiles, cement sheeting, or loose material in a wall cavity: stop work, leave the area, do not sweep or vacuum, close off access and put up a sign, then report to the engineering manager; inspection and clean-up are handed to the surveyor and to a contractor licensed or authorized to handle asbestos.
- The work would drill, cut, chase, or remove part of an old building that has no asbestos register or refurbishment survey for that area: postpone until a competent asbestos surveyor has surveyed the area.
- The survey report states that an area was not accessed or is presumed to contain asbestos: do not work in that area until the surveyor has checked it further.
- Old pipe or boiler insulation, sprayed coatings, or loose fill appears damaged or is shedding: close the room, do not enter, and call a contractor licensed or authorized to handle asbestos.
- Dust or debris from a suspected asbestos material is on clothing, hair, or shoes: do not shake it off, brush it off, or carry it out of the area; stay put, avoid breathing in the dust, and ask the asbestos contractor for help with decontamination.
- Old paint is about to be scraped, sanded, burned, or heated and there is no lead test result from an authorized tester: postpone the work; testing and stripping are handed to a tester and contractor authorized for lead.
- Concrete, brick, or tile is about to be cut or ground indoors without water suppression or on-tool extraction and without a mask that fits the wearer: stop; the supervisor or renovation contractor provides dust control before work continues.
- The work area enclosure is torn, dust is seen escaping into the corridor, air ducts, or guest rooms, or people with no business there enter the area: stop work, clear the area, and report to the engineering manager; the area is reopened only after the contractor, together with the surveyor or industrial hygienist, declares it fit for reoccupation.
Common misinterpretations
Guess what’s wrong first, then open the explanation.
Common misconception
Asbestos was banned long ago, so our building must be asbestos free.
Why is it wrong?
Permenaker 3/1985 prohibited only blue asbestos and the spraying of asbestos. The year of a complete ban in Indonesia cannot be confirmed, so a building’s asbestos status is established by the register and the survey.
Common misconception
Asbestos can be recognized by its color or shape.
Why is it wrong?
Asbestos cannot be identified by its color, and asbestos insulating board is difficult to tell apart from ordinary board. Certainty comes from laboratory analysis of a sample.
Common misconception
As long as it is below the NAB, the room is safe to enter.
Why is it wrong?
The NAB is an average over a particular reference period, and asbestos is classed as a human carcinogen. Examples 1 and 2 show that an average can hide a peak and that a concentration below the threshold still means thousands of fibers inhaled.
Common misconception
Any dust mask is enough.
Why is it wrong?
A mask’s protection depends on its protection factor, its fit to the face, and the way it is worn. The mask is the last line of protection, after dust has been prevented with water or on-tool extraction.
Common misconception
Demolition dust can simply be swept up or vacuumed with an ordinary vacuum cleaner.
Why is it wrong?
A brush spreads asbestos, an ordinary commercial vacuum is not designed for this dust, and Permenaker 3/1985 prohibits compressed air for asbestos dust. Cleaning it up is the work of an authorized contractor.
Links to other chapters
Chapter 37 · Buildings & Facilities on paints and coatings covers old paint. Chapter 36 · Buildings & Facilities on cracks in walls and concrete, Chapter 39 · Buildings & Facilities on floors and tiles, and Chapter 24 · Fluids & Thermal on pipe insulation mention old plaster, vinyl tiles, adhesives, and insulation that may contain asbestos, and brittle asbestos cement sheeting on roofs is in Chapter 35 · Buildings & Facilities on roofs. Dust and the airways are covered in Chapter 36 · Biology & Microbiology on breathing and workplace air, room air quality in Chapter 40 · Buildings & Facilities on indoor air quality, leftover hazardous materials in Chapter 35 · Water & Water Treatment on B3 waste, and work permits in Chapter 2 on the hierarchy of controls and Chapter 76 · Electrical & Control on safe work and work permits.
Exercises and worked solutions
The numbers in the exercises are for practice.
Try to answer first, then open the worked solution.
Measurements during removal give 0.25 fibers/ml for 2 hours and zero for the rest of the working day. Calculate the 8-hour average and the 4-hour average containing those 2 hours, then compare them with the value of 0.1 fibers/ml.
Check my answer
See the worked solution
The exposure total is fibers/ml times hours, so the 8-hour average is fibers/ml and the 4-hour average is fibers/ml. The 8-hour average is below 0.1 fibers/ml and the 4-hour average is above it, so reading the result is left to an industrial hygienist.
A technician is asked to drill a guest room ceiling in a building from the 1990s to fit a new detector, and the asbestos register does not cover that floor. What happens?
Check my answer
See the worked solution
The work is postponed, because an area with no register or survey for that scope must not be assumed to be asbestos free. The engineering manager orders a survey of that ceiling, and the installation continues after the result shows the material is safe to drill or after an authorized contractor has dealt with the asbestos-containing material.
The silica dust concentration near a cut-off saw is 0.6 mg/m³, and the worker wears an APF 20 mask. Is the concentration breathed below the NAB for crystalline silica?
Check my answer
See the worked solution
The concentration behind the mask is mg/m³, above the NAB of 0.025 mg/m³. A mask is not enough on its own, so the cutting needs water or on-tool extraction first.
Paint on a door frame measuring 1.5 m by 0.5 m is to be scraped. What is the area in square feet, and how does it compare with the EPA minor repair exclusion?
Check my answer
See the worked solution
The area is m², that is, square feet, above the 6 square foot exclusion for indoor work. The EPA figure is only a comparison; old paint that has not been tested is treated as lead paint and handled by an authorized contractor.
After heavy rain, a piece of old cement sheeting falls from a roof onto the parking area and breaks. A cleaner is about to sweep it up. What should happen?
Check my answer
See the worked solution
The cleaner does not sweep the piece, because old cement sheeting may contain asbestos and a brush can spread its fibers. The area is closed off and marked, the incident is reported to the engineering manager, and inspection and clean-up are handed to a contractor authorized to handle asbestos.
Why is a refurbishment survey not carried out in a room that is in use, and what is the condition for that room to be occupied again?
Check my answer
See the worked solution
A refurbishment survey is destructive and can therefore release fibers, and the HSE guidance asks for it only in unoccupied areas or areas separated by a full partition. Before people return, the area must be shown to be fit for reoccupation through a thorough visual inspection and, where appropriate, air sampling by an authorized party.
References
External sources
- Peraturan Menteri Ketenagakerjaan Nomor 5 Tahun 2018 tentang Keselamatan dan Kesehatan Kerja Lingkungan Kerjajdih.kemnaker.go.id
- Peraturan Menteri Tenaga Kerja Nomor PER.03/MEN/1985 tentang Keselamatan dan Kesehatan Kerja Pemakaian Asbesjdih.kemnaker.go.id
- Locations of asbestos and taking the right actionhse.gov.uk
- Asbestos: The survey guide (HSG264)hse.gov.uk
- Managing and working with asbestos: Control of Asbestos Regulations 2012, Approved Code of Practice and guidance (L143)hse.gov.uk
- What to do if you discover or accidentally disturb asbestos during your work (em1)hse.gov.uk
- Asbestos - FAQshse.gov.uk
- Construction dusthse.gov.uk
- Renovation, Repair and Painting Program: Work Practicesepa.gov
- Renovation, Repair and Painting Program: Contractorsepa.gov
Revision history
| Date | Version | Change |
|---|---|---|
| November 15, 2026 | 1 | First published |
How to cite
Kurnia (2026). Asbestos and hazardous materials when renovating old buildings: where asbestos is found in a building, surveys before demolition, lead paint, silica dust, separating the work area, and the limits of the work. ARSTEMA Academy. Revised November 15, 2026. arstema.com/en/academy/konsep/asbes-dan-bahan-berbahaya-saat-renovasi-gedung-lama-letak-asbes-dalam-bangunan-survei-sebelum-pembongkaran-cat-bertimbal-debu-silika-pemisahan-area-serta-batas-pekerjaan
Self-check · 3 questions
Check your understanding before moving on
Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.
Safety limits still apply. This quiz tests reasoning; it doesn’t authorize mixing, adjusting, dismantling, live measurement, or field action.
Measurements during removal give 0.25 fibers/ml for 2 hours and zero for the rest of the working day. Calculate the 8-hour average and the 4-hour average containing those 2 hours, then compare them with the value of 0.1 fibers/ml.
A technician is asked to drill a guest room ceiling in a building from the 1990s to fit a new detector, and the asbestos register does not cover that floor. What happens?
The silica dust concentration near a cut-off saw is 0.6 mg/m³, and the worker wears an APF 20 mask. Is the concentration breathed below the NAB for crystalline silica?