    Electrical & Control · Chapter 120Applied

    By Kurnia · Published November 15, 2026 · Version 1 · 21 min read

    Electric vehicle charging stations in hotel parking

    charging modes and connectors, power and dedicated circuits, grounding and RCDs, placement and impact protection, inspection, and energy recording

    A resort hotel already has four electric car charging points in its open-air parking; one unit is hit by a reversing car, the finance department asks why the kWh on the charger screens do not match the submeter, and management wants to bill guests per kWh. This chapter covers electric vehicle charging stations in hotel parking from the building technician’s side: the difference between a private electrical installation and an SPKLU (public electric vehicle charging station) under Permen ESDM Number 1 of 2023, charging modes and connectors with their color markings, power and dedicated circuits, grounding and RCDs, placement and impact protection, routine inspection and damaged units, and energy recording and reconciliation. UK provisions (Approved Document S, OZEV guidance for covered car parks, OZEV technical specifications) and the charging meter tolerances in the US NIST Handbook 44 are used for comparison and presented as data from those countries. Details of modes, connectors, connection capacity, and RCD selection under PUIL are in Chapter 24 · Automotive & Electric Mobility; installing, altering, and testing charging circuits is work for licensed installers.

    Section you’re reading: Chapter opening

    A resort hotel installed four electric car charging points in the open-air parking near its lobby a year ago. One afternoon, a guest’s car reversing out of a bay hit one of the units. The unit housing cracked, the tethered charging cable hung down onto the paving, and its indicator light went out. The next morning the finance department arrived with a different question: the kWh shown on the screens of the four units over a month were lower than the reading of the parking panel submeter, and management wanted to start billing guests per kWh.

    All three landed on the building technician’s desk at once. The damaged unit is declared out of use, the energy difference needs explaining with numbers, and the plan to bill per kWh touches the rules that separate an installation for one’s own use from a public charging station. The technician needs to know the regulatory basis, how the equipment works, the correct placement and protection, inspection, and energy recording.

    Scope

    This chapter covers electric vehicle charging points in the parking areas of hotels, laundries, and hospitals from the side of the building technician who operates and maintains them: the Indonesian regulatory basis, modes and connectors, power and dedicated circuits, grounding and RCDs as far as they need to be recognized, placement and impact protection, inspection, and energy recording. UK and US provisions are used for comparison and presented as data from those countries.

    Topics in other chapters: charging modes, connectors, connection capacity, maximum demand, load management, and RCD selection under PUIL 2020 Part 7-722 are covered in more detail in Chapter 24 · Automotive & Electric Mobility on electric car charging in hotels and buildings; AC and DC charging inside the vehicle in Chapter 7 · Automotive & Electric Mobility on traction batteries and charging; electric vehicle diagnosis in Chapter 10 · Automotive & Electric Mobility; vehicle battery fires in Chapter 9 · Automotive & Electric Mobility; RCD types in Chapter 22; grounding in Chapter 29; emergency switching in Chapter 31; PLN meters and bills in Chapter 112; basement parking ventilation in Chapter 42 · Buildings & Facilities; and small lithium batteries in buildings in the R24 chapter on lithium batteries in buildings (Chapter 17 · Safety).

    Outside the building technician’s authority: designing, installing, connecting, altering, or testing charging circuits, including opening distribution boards, replacing RCDs, and carrying out RCD or grounding tests; opening a charger housing; updating its software; and deciding the business scheme for selling electricity. That work belongs to licensed electrical designers and installers, the charger manufacturer or supplier, SPKLU business entities, and hotel management with its legal advisers. The building technician inspects visually, records, declares units out of use, operates the designated isolating switch, and reports.

    Private installation or SPKLU: the Indonesian regulatory basis

    Regulation of the Minister of Energy and Mineral Resources (Permen ESDM) Number 1 of 2023 on the provision of electric charging infrastructure for battery-based electric motor vehicles replaces Permen ESDM Number 13 of 2020; as of November 2026, JDIH ESDM lists it with the status of revoking Permen 13/2020 and with no record of amendment. The regulation divides recharging facilities into two kinds.

    A private electrical installation (instalasi listrik privat) is a facility within an electricity utilization installation for charging battery-based electric motor vehicles for one’s own use and not for sale. An SPKLU (public electric vehicle charging station) is a charging facility for such vehicles for the public. A private electrical installation may be located outside government offices and housing as long as it is for one’s own use, does not require a business license for the provision of electricity for public use (IUPTLU), and if it is operated by another party, that party must hold a business license for electricity support services (IUJPTL). An SPKLU is provided by an SPKLU business entity holding an IUPTLU and must obtain an SPKLU identity number, which must be displayed at the site.

    The criteria for a private electrical installation under Article 9(3): the meter and limiter can read electricity flow outside peak load hours; the connected capacity is able to carry out recharging; and the final circuit connecting point for the dedicated charging supply path must be single-configured. Article 31 requires a product certificate for equipment whose SNI is made mandatory, competency certification for SPKLU technical personnel, and a Certificate of Operational Worthiness (Sertifikat Laik Operasi, SLO) for private electrical installations and SPKLU; where the SNI is not yet mandatory, products come with the manufacturer’s test results.

    For a hotel, a charging point for the hotel’s own operational cars is a private electrical installation. Selling electricity to guests per kWh is selling to the public, which under the regulation is done by an SPKLU business entity using one of the business schemes in Article 13, for example a station owned and operated by an IUJPTL holder in the operations field while the electricity is sold by an IUPTLU holder. Free charging for staying guests falls between the two; whether it counts as “one’s own use” cannot be confirmed from the text of the regulation, so management raises it with the Directorate General of Electricity or a legal adviser.

    Charging modes and connectors

    A charging mode is a classification of how a vehicle is connected to the supply according to where its control and protection are located. The OZEV guidance for covered car parks, which adapts the UK installation code of practice, summarizes it:

    ModeConnectionControl and protection
    1ordinary domestic outlet, not exceeding 7 kWno control pilot function; emergency use only, not installed in covered car parks for charging
    2domestic outlet or dedicated outlet, not exceeding 15 kWin-cable control box incorporating an RCD and a control pilot function
    3dedicated electric vehicle supply equipment, AC, approximately 7 kW single-phase or 22 kW three-phasecontrol pilot function extending to the permanently connected supply equipment
    4supply equipment converting AC to DC above 22 kW, cable always tetheredcontrol pilot function; the equipment can stop charging if a safety concern arises

    According to that guidance, Mode 3 and Mode 4 units monitor faults within the unit, while Mode 1 and Mode 2 do not, and Mode 1 does not meet UK building guidance. Approved Document S requires at minimum a Mode 3 dedicated system on a dedicated circuit, with a status indicator using lights or a display. For a hotel, a guest charging from an ordinary outlet with a portable Mode 2 cable and a cable reel is not using a charging station, as discussed in Chapter 24 · Automotive & Electric Mobility.

    Permen ESDM 1/2023 sets the connectors and their color markings for SPKLU for vehicles with four or more wheels. Slow charging technology, with an output of up to 7 kW, uses at minimum alternating current charging with a type 2 connector marked with a red cover. Medium (above 7 to 22 kW), fast (above 22 to 50 kW), and ultrafast (above 50 kW) charging technologies use at minimum one of: a type 2 AC connector marked with a red cover, a configuration AA type DC connector marked with a green cover, or a configuration FF type combined AC and DC connector marked with a blue cover. These color markings are checked when a new unit is received.

    Power and dedicated circuits

    AC charging power is calculated from voltage and current:

    P1ph=V IP3ph=3 VLL It=EP ηP_\text{1ph} = V\,I \qquad P_\text{3ph} = \sqrt{3}\,V_\text{LL}\,I \qquad t = \frac{E}{P\,\eta}

    where PP is power (W), VV is line-to-neutral voltage (V), VLLV_\text{LL} is line-to-line voltage (V), II is current per phase (A), tt is charging time (hours), EE is the energy delivered into the battery (kWh), and η\eta is charging efficiency. The power factor is taken as 1; the actual value comes from the unit’s data sheet. The power actually used is the smallest of the capabilities of the unit, the connection, and the charger inside the vehicle (Example 1).

    A dedicated circuit is a final circuit that supplies only the charging point, with no other load on that circuit. Permen ESDM 1/2023 requires it in the wording of a final circuit connecting point for a dedicated path that is single-configured, and the UK Approved Document S requires a dedicated circuit with a minimum nominal rated output of 7 kW.

    The OZEV technical specification for commercial chargepoints adds two points for receiving units: the supply must allow the unit to operate at full rated capacity, and where local supply constrains this, the unit is classified by its actual output; units with multiple outlets are classified by the output of each outlet with all of them operating simultaneously.

    Where capacity is limited, sufficient power is achieved through upgrades to the connection, load balancing, or upgrades to the building’s electrical control room, according to the OZEV infrastructure guidance. Maximum demand and load management are calculated in Chapter 24 · Automotive & Electric Mobility. The building technician prepares load data for the parking panel and makes sure no other load, such as garden lighting, is added to a charging circuit after handover.

    Grounding and RCDs

    The charging cable connects the car’s metal body to the protective conductor of the building installation, so grounding continuity is also monitored by the unit. Permen ESDM 1/2023 requires the current, voltage, and communication control system to be separate for each connector channel; current is supplied continuously when the control system identifies that the current capacity matches and that the conductivity of the connector and of the protective grounding conductor (the regulation uses the English term protective earthing conductor) is in order, and current is cut off on any mismatch or when the battery is full. The protection and safety system has an indicator, for example a pilot light, showing the conductivity of the protective grounding conductor between the installation and the vehicle and the conductivity of the connector, separately for each connector channel. That indicator light is what the technician looks at during inspection.

    An RCD (residual current device) is a device that disconnects a circuit when the current flowing out and back is unbalanced, as explained in Chapter 22. In Mode 2, the RCD is in the control box on the portable cable. The 2013 UK government grant scheme specification states that the integral protective device required for Mode 3 charging is a Type A RCD; the Indonesian provisions under PUIL 2020 Part 7-722, including a separate RCD per connecting point and protection against DC fault current, are covered in Chapter 24 · Automotive & Electric Mobility and Chapter 22. The choice of RCD type and arrangement is the designer’s decision.

    The grounding arrangement is also the designer’s decision. Approved Document S asks for the cable route strategy to be set according to how the charging point’s supply will be grounded. The OZEV infrastructure guidance notes that the current edition of the UK wiring regulations prevents simultaneous contact between different grounding systems, for example between two vehicles charging from different systems or between a charging vehicle and metalwork connected to another grounding system such as a streetlight, and that equipment of different systems needs to be at least 2.5 m apart; any additional grounding needed is installed, and grounding locations for future points are identified. The 2.5 m figure is a UK provision; for an Indonesian technician, it is a reason to ask the designer whenever a lamp post, metal fence, or another panel is near a charging point (Example 3). Grounding theory is in Chapter 29.

    Placement and impact protection

    Permen ESDM 1/2023 requires an SPKLU to be provided at a location that is easy to reach, with dedicated SPKLU parking, and that does not disturb security, safety, order, and the smooth flow of traffic. Approved Document S adds that the location should suit charging inlets on any side, often best at one corner of the parking space, and that at least one accessible parking space has access to a charging point.

    The OZEV guidance for covered car parks gives a list of measures that reduce damage to units and cables:

    1. Crash protection for the unit, in the form of bollards or physical barriers designed to UK standards BS 6180 or PAS 68.
    2. Speed limits in the parking area and a layout that reduces collisions: good sight lines and lighting, sufficient turning space, a one-way system, and rubber pads on columns.
    3. The unit positioned so that the cable reaches the vehicle with the shortest possible length, not lying where other vehicles drive or where people walk.
    4. Security cameras with clear signage to deter damage.
    5. A unit whose cable is easy to return to its rest position.
    6. The unit not blocking the only means of escape, and within reach of fire service hoses.
    7. A manual isolating switch that cuts the entire supply to the units, usually at the distribution board or circuit serving them, labeled to show which units it isolates, and located near the firefighting entrance or the fire alarm panel.

    For spaces prepared for future units, Approved Document S asks for space for vehicle barriers where needed, for example 500 mm around the location. In basement parking, ventilation follows Chapter 42 · Buildings & Facilities and vehicle fires Chapter 9 · Automotive & Electric Mobility. Impact protection is installed before the unit is put into operation; the unit in the opening case had no bollards at all.

    Routine inspection and damaged units

    The OZEV guidance for covered car parks calls for routine inspections by a responsible organization, because inspections find damage that the unit’s internal monitoring does not recognize. A damaged unit is removed from use immediately, because charging with a faulty unit can start a fire, and the fault is reported to the manufacturer for rectification. The OZEV technical specification for commercial chargepoints requires manufacturers to supply an on-site 3-year warranty on parts and installation, so repair of a unit still under warranty is not done in-house.

    A visual inspection by the building technician without opening the unit can include:

    1. The housing is intact, not cracked, not tilted, and shows no collision marks; bollards are in place.
    2. The charging cable and connector are not crushed, not stripped, show no heat marks, and are stowed in place; the connector’s color cover matches its type.
    3. The status and grounding indicator lights are normal, and the screen shows no fault message.
    4. There is no burning smell, unusual noise, or standing water around the unit.
    5. The isolating switch label, the SPKLU identity number if any, and the operating instructions are legible.
    6. The meter reading of each unit is recorded together with the parking panel submeter reading.

    A unit that fails items 1 to 4 is declared out of use, isolated at the designated isolating switch, and handed to the supplier. RCD, grounding, and insulation tests are carried out by the installer according to the periodic inspection schedule.

    Energy recording

    Energy recording explains the electricity cost, provides the basis for billing if electricity is sold, and finds problem units. Permen ESDM 1/2023 requires the online application of an SPKLU business entity to contain, among other things, the amount of electricity for each connector and the kWh used and sold, and requires the reports of integrated IUPTLU holders to contain consumption and tariff data for vehicle charging for all private electrical installations. The 2013 UK grant specification requires a certified meter for each outlet, with a display of the energy used and a data output.

    Tariffs are also regulated. For private electrical installations other than public transport, the electricity tariff follows its tariff class. The tariff from an SPKLU business entity to the vehicle owner is the purchase cost of electricity per kWh under the special service tariff with a multiplying factor N of at most 1.5, set by the SPKLU business entity; a service fee per charging session applies only to fast and ultrafast charging, and is not charged for slow and medium charging. Reading PLN bills and tariff classes is in Chapter 112.

    Meter accuracy determines whether the figures are fit to be the basis of a bill. The 2026 edition of NIST Handbook 44 in the United States, for charging equipment used as a basis of sale, gives test tolerances for AC systems of 1.0 percent at acceptance and 2.0 percent in maintenance, applying equally to over- and under-registration, and a minimum measured quantity not exceeding 0.5 kWh for AC equipment. Meter error is calculated with:

    ε=Eshown−ErefEref×100\varepsilon = \frac{E_\text{shown} - E_\text{ref}}{E_\text{ref}} \times 100

    where ε\varepsilon is error (percent), EshownE_\text{shown} is the energy displayed by the unit (kWh), and ErefE_\text{ref} is the energy according to the reference meter (kWh). These tolerances are US data; Indonesian provisions on meters for transactions are not covered here.

    Energy reconciliation is comparing the total kWh of all units with the kWh of the submeter supplying them over the same period. A difference does not automatically mean a meter is wrong: the submeter also records the units’ standby consumption and cable losses, while the unit meters record only the energy delivered to vehicles (Example 4). A difference that stays large after that is a reason to ask the supplier to check the meters.

    Worked example

    The numbers in the examples below are practice numbers unless their origin is stated.

    Example 1: a staying guest with a half-empty battery. A guest’s car with a 64 kWh battery arrives at 25 percent and wants 80 percent the next morning, so the energy into the battery is 0.55×64=35.20.55 \times 64 = 35.2 kWh. A single-phase 32 A unit gives 230×32=7,360230 \times 32 = 7{,}360 W, about 7.4 kW, which under Permen ESDM 1/2023 counts as medium charging technology because it is above 7 kW. With an efficiency of 0.9, charging takes 35.2/(7.36×0.9)=5.335.2/(7.36 \times 0.9) = 5.3 hours. A three-phase 16 A unit gives 3×400×16=11,085\sqrt{3} \times 400 \times 16 = 11{,}085 W, about 11.1 kW, but if the charger inside the car is single-phase 7.4 kW only, the time stays 5.3 hours.

    Example 2: number of points under Approved Document S (UK). Under Approved Document S, a new non-residential building with more than 10 parking spaces needs one charging point and cable routes for at least one in every five remaining parking spaces; a hotel counts as non-residential because its rooms are not dwellings. A 41-space car park needs 1 point and cable routes for 40/5=840/5 = 8 spaces. A 43-space car park needs 1 point and 42/5=8.442/5 = 8.4, rounded up to 9 spaces, because “at least one in five” may not fall short. That is a UK rule for new buildings, not an obligation for hotels in Indonesia.

    Example 3: a lamp post near the unit and barrier space. A floor-standing unit measuring 0.40 m by 0.30 m is planned 1.8 m from a parking lamp post supplied from another panel with a different grounding arrangement. Against the UK distance of 2.5 m between equipment of different systems, the shortfall is 2.5−1.8=0.72.5 - 1.8 = 0.7 m, so the unit is moved or the designer sets another solution. With 500 mm of barrier space, the reserved area is (0.40+2×0.5)×(0.30+2×0.5)=1.4×1.3=1.82(0.40 + 2 \times 0.5) \times (0.30 + 2 \times 0.5) = 1.4 \times 1.3 = 1.82 m², kept clear of parking lines and vehicle paths.

    Example 4: a month’s energy reconciliation. Four units recorded 410.0 kWh in 30 days, while the parking panel submeter recorded 421.0 kWh. The difference is 421.0−410.0=11.0421.0 - 410.0 = 11.0 kWh, that is 11.0/421.0=2.6111.0/421.0 = 2.61 percent of the submeter. The data sheet gives standby consumption of 3 W per unit, so over 720 hours the four units use 4×3×720=8,6404 \times 3 \times 720 = 8{,}640 Wh, that is 8.64 kWh. The remaining difference is 11.0−8.64=2.3611.0 - 8.64 = 2.36 kWh, or 2.36/421.0=0.562.36/421.0 = 0.56 percent, reasonable for cable losses and the difference in accuracy between two meters.

    Example 5: price per kWh through an SPKLU business entity. With a special service tariff of IDR 1,650 per kWh, the multiplying factor N of at most 1.5 under Permen ESDM 1/2023 limits the energy price to 1.5×1,650=2,4751.5 \times 1{,}650 = 2{,}475 rupiah per kWh. The 35.2 kWh charge in Example 1 costs at most 35.2×2,475=87,12035.2 \times 2{,}475 = 87{,}120 rupiah for its energy. Because the unit is medium charging, no per-session service fee is charged.

    Example 6: a meter test against the NIST tolerances (US). The supplier tests one AC unit against a reference meter. The reference meter records 10.00 kWh and the unit displays 10.15 kWh, so the error is (10.15−10.00)/10.00×100=1.5(10.15 - 10.00)/10.00 \times 100 = 1.5 percent. Under NIST Handbook 44, that is outside the 1.0 percent acceptance tolerance for a new unit but within the 2.0 percent maintenance tolerance for a unit already in use. A 0.3 kWh session is below the 0.5 kWh minimum measured quantity, so its accuracy is not guaranteed by that provision. For the hotel, the test result is a reason to ask the supplier to calibrate the meter before it is used for billing.

    Stop conditions

    1. A unit has been hit, its housing is cracked or tilted, or its cable or connector is stripped, crushed, melted, or smells burnt: declare the unit out of use, put up a sign, isolate its supply at the designated isolating switch if the procedure allows and the switch can be reached safely, then hand it to the supplier or a licensed installer; do not open the unit housing or touch exposed cable.
    2. The unit’s RCD or protective device trips repeatedly, or the grounding indicator shows a fault: do not reset it repeatedly and do not bypass the protection; switch the unit off and hand it to a licensed installer and the supplier.
    3. A guest is charging from an ordinary outlet with a portable cable, cable reel, or adapter: stop the charging together with the guest and direct them to an available charging point; the technician does not assemble a substitute connection.
    4. There is a request to add a unit, move a unit, connect a unit to an existing circuit, add another load to a charging circuit, or test a circuit: hand it to a licensed designer and installer; a new or altered unit is not operated before it has been inspected, tested, and holds a Certificate of Operational Worthiness.
    5. A vehicle on charge is smoking, smells, or hisses: do not approach it or unplug the connector; keep people away, raise the alarm, call the fire service, and isolate the unit’s supply at the isolating switch near the firefighting entrance if designated by the procedure and it can be reached safely, following Chapter 9 · Automotive & Electric Mobility.
    6. Management wants to bill guests per kWh from an installation recorded as a private electrical installation, or a unit meter differs widely from the submeter after standby consumption is accounted for: postpone billing; hand the business scheme decision to management and the legal adviser, and the meter check to the supplier.

    Common misinterpretations

    Guess what’s wrong first, then open the explanation.

    Common misconception

    An outlet on the parking wall is enough for an electric car.

    Why is it wrong?

    An ordinary outlet with a portable cable is Mode 2, while a charging station is a Mode 3 or Mode 4 unit on a dedicated circuit with fault monitoring. A cable reel and a garden lighting outlet are not a charging station.

    Common misconception

    A 22 kW unit always charges three times faster.

    Why is it wrong?

    The power used is the smallest of the unit, the connection, and the charger inside the car. A car with a single-phase 7.4 kW charger still takes about 7.4 kW from a 22 kW unit.

    Common misconception

    A difference between the unit screens and the submeter means the meter is broken.

    Why is it wrong?

    The submeter also records the units’ standby consumption and cable losses. A difference becomes a finding only if it stays large after those factors are accounted for.

    Common misconception

    The hotel may sell electricity to guests because the chargers belong to the hotel.

    Why is it wrong?

    A private electrical installation is for one’s own use and not for sale; selling per kWh to the public goes through an SPKLU business entity.

    Common misconception

    Bollards are only for basement parking.

    Why is it wrong?

    A unit in open-air parking is just as easily hit by a reversing car, as in the opening case; impact protection follows the unit’s position relative to vehicle paths.

    Chapter 24 · Automotive & Electric Mobility on electric car charging in hotels and buildings is the companion to this chapter: connection capacity, load management, voltage drop, and RCD selection under PUIL are calculated there. Chapter 7 · Automotive & Electric Mobility on traction batteries explains the charger inside the vehicle, Chapter 9 · Automotive & Electric Mobility vehicle battery fires, Chapter 112 PLN bills, and Chapter 42 · Buildings & Facilities basement parking ventilation. The R24 chapter on lithium batteries in buildings (Chapter 17 · Safety) covers electric bicycles and scooters that are often parked in the same area.

    Exercises and worked solutions

    The numbers in the exercises are for practice.

    Try to answer first, then open the worked solution.

    1. What is the power of a three-phase 400 V 32 A unit with a power factor of 1, and which charging technology does it fall under in Permen ESDM 1/2023?

      Check my answer
      See the worked solution

      The power is 3×400×32=22,170\sqrt{3} \times 400 \times 32 = 22{,}170 W, about 22.2 kW, slightly above the 22 kW limit. Units like this are usually rated 22 kW on their nameplate and fall under medium charging technology (above 7 to 22 kW), so classification uses the output declared for the unit, not a rough calculation with a power factor of 1.

    2. A hotel operational car with a 50 kWh battery needs charging from 30 to 90 percent with a 7.4 kW unit and an efficiency of 0.9. How long does it take?

      Check my answer
      See the worked solution

      The energy delivered is 0.6×50=300.6 \times 50 = 30 kWh, so it takes 30/(7.4×0.9)=4.530/(7.4 \times 0.9) = 4.5 hours. A car that arrives in the afternoon can be full before morning use, so a 7.4 kW unit is enough for that fleet.

    3. A new hotel car park designed under Approved Document S has 26 spaces. How many points and cable routes are needed under that UK rule?

      Check my answer
      See the worked solution

      One charging point and cable routes for at least 25/5=525/5 = 5 of the 25 remaining spaces. That figure is a UK building provision, so in Indonesia it serves as an indication of preparation, not an obligation.

    4. The connector fitted to a DC unit is marked with a green cover. Which connector is it under Permen ESDM 1/2023?

      Check my answer
      See the worked solution

      A green cover marks a configuration AA type DC connector. A configuration FF type combined AC and DC connector is marked blue and a type 2 AC connector red, so the cover color helps confirm that the unit received matches the order.

    5. Four units recorded 512.0 kWh and the submeter 530.0 kWh in 30 days, with standby consumption of 3 W per unit. What is the difference after standby consumption is accounted for?

      Check my answer
      See the worked solution

      Standby consumption is 4×3×720=8,6404 \times 3 \times 720 = 8{,}640 Wh or 8.64 kWh, and the raw difference is 530.0−512.0=18.0530.0 - 512.0 = 18.0 kWh. The remainder is 18.0−8.64=9.3618.0 - 8.64 = 9.36 kWh, that is 9.36/530.0=1.779.36/530.0 = 1.77 percent, well above the 0.56 percent in Example 4, so the supplier is asked to check the unit meters.

    6. During the morning inspection, one unit’s screen shows a grounding fault message, although a guest used it overnight without problems. What does the technician do?

      Check my answer
      See the worked solution

      The unit is declared out of use and switched off at the designated isolating switch, because the grounding light and message are a protective function required by the regulation, not a display glitch. The technician does not reset it repeatedly or open the unit, and hands the check to a licensed installer and the supplier.

    References

    External sources

    • Peraturan Menteri Energi dan Sumber Daya Mineral Republik Indonesia Nomor 1 Tahun 2023 tentang Penyediaan Infrastruktur Pengisian Listrik untuk Kendaraan Bermotor Listrik Berbasis Bateraijdih.esdm.go.id
    • Covered car parks - fire safety guidance for electric vehiclesassets.publishing.service.gov.uk
    • Approved Document S: Infrastructure for charging electric vehicles, 2021 editionassets.publishing.service.gov.uk
    • Electric vehicle chargepoint and infrastructure specificationsgov.uk
    • Commercial chargepoints: minimum technical specificationgov.uk
    • Grant Scheme for the installation of plug-in vehicle chargepoints on the UK Government and wider public sector estateassets.publishing.service.gov.uk
    • 2026 NIST Handbook 44 Section 3.40nist.gov

    Revision history

    DateVersionChange
    November 15, 20261First published

    How to cite

    Kurnia (2026). Electric vehicle charging stations in hotel parking: charging modes and connectors, power and dedicated circuits, grounding and RCDs, placement and impact protection, inspection, and energy recording. ARSTEMA Academy. Revised November 15, 2026. arstema.com/en/academy/konsep/stasiun-pengisian-kendaraan-listrik-di-parkir-hotel-mode-dan-konektor-pengisian-daya-dan-sirkit-khusus-pembumian-dan-rcd-penempatan-dan-pelindung-tabrak-pemeriksaan-serta-pencatatan-energi

    Self-check · 3 questions

    Check your understanding before moving on

    Write your answer in your own words, then compare it with the worked solution from this chapter’s exercises. The system doesn’t judge open answers as right or wrong; you decide which parts you’ve understood.

    0/3rated
    1

    What is the power of a three-phase 400 V 32 A unit with a power factor of 1, and which charging technology does it fall under in Permen ESDM 1/2023?

    2

    A hotel operational car with a 50 kWh battery needs charging from 30 to 90 percent with a 7.4 kW unit and an efficiency of 0.9. How long does it take?

    3

    A new hotel car park designed under Approved Document S has 26 spaces. How many points and cable routes are needed under that UK rule?

    Self-assessment progress0%

    Nearby chapters

    NextForce, torque, rotation, and power transmission

    Reading order by shelf: Mechanical & Mechatronics · Chapter 1.

    Same disciplineVoltage, current, resistance, and power

    Another chapter in Electrical & Control.